1 Predimensionamiento De Columnas, Vigas Y Zapatas Datos: Niveles = 6 Cv = 500 kg/m 2 Cm = 300 kg/m 2 Cv az = 100 kg/m 2 Cp del suelo = 1.03 kg/cm 2 σ del suelo = 1903 kg/m 3 S/C = 500 kg/ m 2 E. piso = 0.15 m F’c = 210 kg/cm 2 F’y = 4200 kg/cm 2 Φ de columna central y lateral = ¾” Φ de columna esquina = 5/8” 1. PREDIMENSIONAMIENTO DE COLUMNAS. COLUMNA 1: At 1 = 5x4.25=21.25 m2 PG p =1.2(300)+1.6(500) =1160kg/m 2 PG az = 1.2 (300)+1.6 (100) = 520 kg/m 2 Pt = (5x1160x21.25)+ (520x1x21.25)=134300kg 1º piso: Asc= (1.1)(134300) (0.25)(210) = 2813.90 cm 2 = (53.05) 2 = 55x55 cm

Embed Size (px)

description

columnas, vigas y zapatas

Transcript of Analisis Ultima Version

  • 1

    Predimensionamiento De

    Columnas, Vigas Y Zapatas Datos: Niveles = 6

    Cv = 500 kg/m2

    Cm = 300 kg/m2

    Cvaz = 100 kg/m2

    Cp del suelo = 1.03 kg/cm2

    del suelo = 1903 kg/m3

    S/C = 500 kg/ m2

    E. piso = 0.15 m

    Fc = 210 kg/cm2

    Fy = 4200 kg/cm2

    de columna central y lateral =

    de columna esquina = 5/8

    1. PREDIMENSIONAMIENTO DE COLUMNAS. COLUMNA 1:

    At1 = 5x4.25=21.25 m2

    PGp=1.2(300)+1.6(500) =1160kg/m2

    PGaz = 1.2 (300)+1.6 (100) = 520 kg/m2

    Pt = (5x1160x21.25)+ (520x1x21.25)=134300kg

    1 piso:

    Asc=(1.1)(134300)(0.25)(210) = 2813.90 cm2= (53.05)2= 55x55 cm

  • 2

    2 piso:

    Asc=(1.1)(109650)(0.25)(210) = 2297.43 cm2= (47.93)2= 50x50 cm

    3 piso:

    Asc=(1.1)(85000)(0.25)(210) = 1780.95 cm2=(42.20)2 = 45x45 cm

    4 piso:

    Asc=(1.1)(60350)(0.3)(210) = 1053.73 cm2= (32.46)2= 35x35 cm

    5 piso:

    Asc=(1.1)(35700)(0.3)(210) = 623.33cm2= (24.97)2= 25x25 cm

    6 piso:

    Asc=(1.1)(35700)(0.3)(210) = 623.33cm2= (24.97)2= 25x25 cm

    COLUMNA 2:

    At =5x2.25=11.25 m2

    PGp =1.2(300)+1.6(500 )=1160kg/m2

    PGaz = 1.2 (300)+1.6 (100) = 520 kg/m2

    Pt = (5x1160x11.25)+ (520x11.25) =71100kg

    1 piso:

    Asc=(1.25)(71100)(0.25)(210) = 1692.86 cm2= (41.14)2= 45x45 cm

    2 piso:

    Asc=(1.25)(58050)(0.25)(210) = 1382.14 cm2= (37.18)2= 40x40 cm

  • 3

    3 piso:

    Asc=(1.8)(45000)(0.25)(210) = 1071.43 cm2= (32.71)2= 35x35 cm

    4 piso:

    Asc=(1.25)(31950)(0.25)(210) = 760.71 cm2= (27.58)2= 30x30 cm

    5 piso:

    Asc=(1.25)(18900)(0.25)(210) = 450cm2= (21.21)2= 25x25 cm

    6 piso:

    Asc=(1.25)(18900)(0.25)(210) = 450cm2= (21.21)2= 25x25 cm

    COLUMNA 3:

    At=4.25x2.5 =10.625 m2

    PGp=1.2(300)+1.6(500) =1160kg/m2

    PGaz= 1.2 (300)+1.6 (100) = 520 kg/m2

    Pt= (5x1160x10.625)+ (520x10.625) = 67150kg

    1 piso:

    Asc=(1.25)(67150)(0.25)(210) = 1598.81 cm2= (39.99)2= 40x40 cm

    2 piso:

    Asc=(1.25)(54825)(0.25)(210) = 1305.36 cm2= (36.13)2= 40x40 cm

    3 piso:

    Asc=(1.25)(42500)(0.25)(210) = 1011.91 cm2= (31.81)2= 35x35 cm

  • 4

    4 piso:

    Asc=(1.25)(30175)(0.25)(210) = 718.452 cm2= (26.8)2= 30x30 cm

    5 piso:

    Asc=(1.25)(17850)(0.25)(210) = 425cm2= (20.6)2= 25x25 cm

    6 piso:

    Asc=(1.25)(17850)(0.25)(210) = 425cm2= (20.6)2= 25x25 cm

    COLUMNA 4:

    At=2.25x2.5=5.625 m2

    PGp=1.2(300)+1.6(500)=1160kg/m2

    PGaz= 1.2 (300)+1.6 (100)= 520 kg/m2

    Pt= (5x1160x5.625)+ (520x5.625)=35550kg

    1 piso:

    Asc=(1.5)(35550)(0.20)(210) = 1269.64 cm2= (35.6)2= 40x40 cm

    2 piso:

    Asc=(1.5)(29025)(0.20)(210) = 1036.61 cm2= (32.19)2= 35x35 cm

    3 piso:

    Asc=(1.5)(22500)(0.20)(210) = 803.57 cm2= (28.3)2= 30x30 cm

    4 piso:

    Asc=(1.5)(15975)(0.20)(210) = 570.54 cm2= (23.9)2= 25x25 cm

    5 piso:

    Asc=(1.5)(9450)(0.20)(210)= 337.5 cm2= (18.37)2= 25x25 cm

  • 5

    6 piso:

    Asc=(1.5)(2925)(0.20)(210)= 104.46 cm2= (10.22)2= 25x25 cm

    Resumen de datos

  • 6

    2. PREDIMENSIONAMIENTO DE VIGAS:

    Principales:

    P=()(10)= (5)(10)= 0.5

    b=()(20)= (5)(20)=0.25

    Vp = 50cm x 25cm

    Secundaria:

    P=()(12)=(4.5)(12)= 0.375= 40

    b=()(20)=(4.5)(20)=0.225= 25

    Vs =40 cm x 25cm

    3. PREDIMENSIONAMIENTO DE ZAPATAS: Zapata N 1

    CVT = (5000(5)+100) (21.25) = 55250Kg = 55.25Tn

    CMT = (300) (21.25) (6) =38250Kg = 38.25Tn

    Peralte efectivo

    d = 0.08 * Ac *

    0.004 * A * Fy d = 0.08 * 1.905 *

    4200

    210 0.004 * 1.905 * 4200 d = 44.17 32

    Altura de la zapata ser:

    hz = d + r + b = 44.17 + 10 +1.588 = 55.758cm = 60cm = 0.6m

  • 7

    El peralte efectivo de diseo ser:

    d = 60 10 1.588 = 48.41cm = 0.4841m

    Esfuerzo neto del terreno

    = 1.03 (1002) 1903(. 6) 500 24008(.15) = 6858.2

    2= 6.858/2

    rea de zapata

    Az = .n

    Az = (.+.)./ = 13.6342

    Lv1 = Lv2

    T = S = 13.634 (..

    ) = 3.692 3.7

    S = 3.7m T = 3.7m

    LV1 = LV2 = ..

    = 1.575

    Reaccin ultima

    Wnu = (.)(.)+.(.)(.) = . = 9810/2

    verificacin de cortante

    vc > Vu (0.53) ()d > Wnu(S)(LV d) 0.75(0.53)210(10)(3.70)(0.4841) > 9.81(3.7)(1.575 0.4841) 103.18 > 39.596

  • 8

    corte por punzonamiento

    m = d + t1 = 0.4841+0.55 = 1.034m

    n = d + t2 = 0.4841+0.55 = 1.034m Vu < Vc

    Vu = Pdin Wnu (m) (n)

    Vu = 134.3 9.81 (1.034)2 = 123.812Tn

    bo = 2m + 2n = 4(1.034) = 4.136m

    = 0.550.55 = 1

    (0.27)(2 + 4

    ) Vc (0.27)(

    + 2)

    1.1

    0.75(0.27) 2 + 41210 (10)(4.136)(0.4841) = 352.53

    Vc 0.75(0.27) (40)(.4841)4.136 + 2 210 (10)(4.136)(0.4841) = 392.595

    0.75 1.1 210 (10)(4.136)(0.4841) = 239.375 Acero

    Mu = 2

    (1)2

    Mu = 9.812

    (1.575)2 (3.7) = 45.02

    = 45.02 105/

  • 9

    rea del acero

    As =

    (2

    ) = As=()(0.85)()()

    45.021050.9(4200)(48.41

    2) = (0.85)(210)(370)4200

    50.021056.6045104 = 48.41 0.52

    0.52 48.41 + 75.736 = 0 = 48.41 48.412 4(0.5)(75.736) 1 = 48.41 46.81

    = . As1= 45.0105

    0.9(4200)(48.411.5912

    ) = . As2= 1.591(0.85)(210)(370)4200 = . As=25.018

    Verificacin de acero mnimo

    As> As 25.0188>0.0018 (48.41) (370)

    25.018>32.241 As = 32.241

    Nv = 32.241

    2= 16.12 17

    S = 3702(2.75)1.588

    16= 22.09 0.22

    Lv =370 2(7.5) = 355 = 3.55

  • 10

    17 @ 0.22

    Zapata N 2

    CVT = (500(5)+100) (11.25) = 29250Kg = 29.25Tn

    CMT = (300) (11.25) (6) =20250Kg = 20.25Tn

    Peralte efectivo

    d = 0.08 * Ac *

    0.004 * A * Fy d = 0.08 * 1.905 *

    4200

    210 0.004 * 1.905 * 4200 d = 44.17 32

    Altura de la zapata ser:

    hz = d + r + b= 44.17 + 10 +1.588 = 55.758cm = 60cm = 0.6m

    El peralte efectivo de diseo ser:

    d = 60 10 1.588 = 48.41cm = 0.4841m

    Esfuerzo neto del terreno

    = 1.03 (1002) 1903(. 6) 500 24008(.15) = 6858.2

    2= 6.858/2

    rea de zapata

    Az = .n

    Az = (.+.)./ = 7.222

  • 11

    Lv1 = Lv2

    S= Lv2 + t2 Lv2 = S- t2

    T= 2 Lv1 + t1 Lv1= 12

    2AZ=T2-T (t1-2t2)

    2(7.22)= T2-T (0.45-2(0.45))

    14.44= T2 + 0.45T

    0= T2 + 0.45T -14.44

    = 0.45 0.452 4(1)(14.44)2 = 3.585

    2S2=AZ-S (t1-2t2)

    2S2=7.22-S (0.45-2(0.45)) S = 0.450.4524(2)(7.22)4

    = 2.015

    Lv2 = 2.015-0.45 = 1.565

    Lv1 =..

    =1.567

    Lv2=Lv1=1.60

    S=1.6+ (0.45)=2.05 m

    T=2(1.6)+ (0.45)= 3.65 m

    Reaccin ultima

    Wnu = (.)(.)+.(.)(.)(.) = . = 9570/2

    m = d + t1 = 0.4841+0.45 = 0.934m

    n = d + t2 = 0.4841+0.45 = 0.934m

  • 12

    verificacin de cortante EJE x

    vc > Vu (0.75) ()d > Wnu(S)(LV d) 0.75(0.53)210(10)(3.65)(0.4841) > 9.57(3.65)(1.6 0.4841) 101.783 > 38.979 EJE y

    (0.75) ()d > Wnu(S)(LV d) 0.75(0.53)210(10)(2.05)(0.4841) > 9.57(2.05)(1.6 0.4841) 57.166 > 21.8923

    corte por punzonamiento Vu < Vc

    Vu = Pdin Wnu (m) (n)

    Vu = 71.58 9.57 (0.934)2 = 63.23 Tn

    bo = 2m + 2n = 4(0.934) = 3.736m

    = 0.450.45 = 1

    (0.27)(2 + 4

    ) Vc (0.27)(

    + 2)

    1.1

  • 13

    0.75(0.27) 2 + 41210 (10)(3.736)(0.4841) = 318.44

    Vc 0.75(0.27) (30)(0.4841)3.736 + 2 210 (10)(3.736)(0.4841) = 312.46

    0.75 1.1 210 (10)(3.736)(0.4841) = 216.225 Acero

    Mu =

    2(1)2

    Mu = 9.572

    (1.6)2 (3.65) = 44.71 . = 44.71 105/

    rea del acero

    As =

    (2

    ) = As=()(0.85)()()

    44.711050.9(0.85)(210)(365) = 48.41 a 0.5 a2

    0.52 48.41 + 76.25 = 0 = 48.41 48.412 4(0.5)(76.25) 1 = 48.41 46.81

    = . As1= 44.711050.9(4200)(48.41(0.51.6)) = .

    As2= 1.6(0.85)(210)(365)4200 = . As=24.84

    Verificacin de acero mnimo

    As> As 24.84>0.0018 (48.41) (365)

  • 14

    24.84> 31.811 As =31.81 Nv = 31.81

    2= 15.91 16

    S = 3652(7.5)1.588

    15= 23.22 24 0.24

    Lv =205 2(7.5) = 190 cm = 1.9

    16 @ 0.24 Ast =

    ()()

    =(31.81)(205)

    365= 17.87 cm2

    Nv = (17.87)

    2= 8.9359

    Se= (205)(27.5)(1.588)

    8=23.55 cm=0.24 m

    Lv=365-(2*7.5)=350=3.5m

    9 @ 0.24

    Zapata N 3

    CVT = (5000(5)+100) = 29.25Tn

    CMT = (300) (6) (11.25) = 20.25Tn

    Peralte efectivo

    d = 0.08 * Ac *

    0.004 * A * Fy d = 0.08 * 1.905 *

    4200

    210 0.004 * 1.905 * 4200 d = 44.17 32

    Altura de la zapata ser: hz = d + r + b= 44.17 + 10 +1.588 = 55.758cm = 60cm = 0.6m

  • 15

    El peralte efectivo de diseo ser:

    d = 60 10 1.588 = 48.41cm = 0.4841m

    Esfuerzo neto del terreno

    = 1.03 (1002) 1903(. 6) 500 24008(.15) = 6858.2

    2= 6.858/2

    rea de zapata

    Az = .n

    Az = (.+.)

    ./ = 6.8172

    Lv1 = Lv2

    S = Lv2 + t2 Lv = S t2

    T = 2Lv1 + t1 Lv1 = 1

    2

    2Az = T2 T(t1-2t2)

    0 = T2 + 0.40T-13.634

    T=0.44(13.634)+0.42

    2

    T=3.5m

    S = 0.4426.817+0.42

    4

    S = 1.95m

    Lv2 = 1.949 0.4 = 1.549

    Lv1 = (3.498 0.4)/2 = 1.549

  • 16

    Lv2=Lv1=1.55m

    S = 1.55 + 0.4 =1.95m

    T = 2*1.55 + 0.4 = 3.50m

    Reaccin ultima

    Wnu = (.)(.)+.(.)

    .. = .

    verificacin de cortante

    Eje X vc > Vu

    (0.53) ()d > Wnu(S)(LV d) 0.75(0.53)210(10)(3.5)(0.4841) > 9.839(3.5)(1.55 0.4841) 97.6 > 36.71

    Eje Y 0.75(0.53)210(10)(1.95)(0.4841) > 9.839(1.95)(1.55 0.4841) 54.38 > 20.45

    verificacin por punzonamiento

    m = d + t1 = 0.4841 + 0.4 = 0.884m

    n = d + t2 = 0.4841 + 0.4 = 0.884m

    V = 67.115 - 9.839(0.884)2 = 59.46Tn

    bo = 3(0.884) = 2.652m

    = 0.40.4 = 1

  • 17

    0.75(0.27) 2 + 41210 (10)(2.652)(. 4841) = 226.04

    Vc 0.75(0.27) (30)(.4841)2.802 + 2210 (10)(2.652)(. 4841) = 281.66

    0.75 1.1 210 (10)(2.652)(. 4841) = 153.49 rea del acero

    As =

    (2

    ) = As=()(0.85)()()

    0.9(0.85)() = 0.52

    41.371050.9(0.85)(210)(350) = 48.41 0.52

    0.52 48.41 + 73.576 = 0 = 48.41 48.412 4(0.5)(73.576) 1 = 48.41 46.81

    = . As1= 41.371050.9(4200)(48.410.51.544) = .

    As2= 1.544(0.85)(210)(350)4200 = . As = 22.97

    Verificacin de acero mnimo

    As >Aminimo 22.97 >0.0018 (48.41) (350) 22.97 >30.498 As = 30.498

  • 18

    Area del acero longitudinal x

    Nv = 30.498

    2= 15.249 16

    Se = 3502(7.5)1.588

    15= 22.23 0.23

    Lv = 195 2(7.5) = 180cm = 1.8

    16 @ 0.23 rea de acero en la seccin transversal Y

    AST=

    = 31.84205

    365= 17.872

    Nv = 16.962

    = 8.495 9 Se =

    1952(7.5)1.5888

    = 22.3 0.23 Lv = 350 2(7.5) = 335cm = 3.5

    9 @ 0.23

    Zapata N 4

    CVT = (500(5)+100) (5.625) = 14625 kg = 14.625Tn

    CMT = (300) (5.625) (6) =10125 Kg = 10.125 Tn

    Peralte efectivo

    d = 0.08 * Ac * 0.004 * A * Fy

    d = 0.08 * 1.588 * 4200210 0.004 * 1.588 * 4200

    d = 36.82 26.68

    Altura de la zapata ser:

  • 19

    hz = d + r + b= 36.82 + 10 +1.588 = 48.408cm = 50cm = 0.5m

    Por condiciones de diseo la altura de la zapata ser 60 cm

    El peralte efectivo de diseo ser:

    d = 60 10 1.588 = 48.41cm = 0.4841m

    Esfuerzo neto del terreno

    = 1.03 (1002) 1903(. 6) 500 24008(.15) = 6858.2

    2= 6.858/2

    rea de zapata

    Az = .n

    Az = (.+.)

    ./ = .P2

    Debe cumplir que:

    Lv1 = Lv2 S= Lv2 + t2 Lv2 = S- t2

    T= Lv1 + t1 Lv1= 1

    Az = T2-T (t1-t2)

    3.61= T2-T (0.40-0.40)

    T=1.9m

    Az = S2-S (t1-2t2)

    3.61= S2-S (0.40-0.40) S = 1.9 m Lv2=1.9-0.4=1.5 m

  • 20

    Reaccin ultima

    Wnu = (.)(.)+.(.)(.) = . = 9850/2

    m = d + t1 = 0.4841+0.40 = 0.884m

    n = d + t2 = 0.4841+0.40 = 0.884m

    bo= m+n=1.768 Bc=0.40/0.40 =1

    verificacin de cortante

    (0.75) ()d > Wnu(S)(LV d) 0.75(0.53)210(10)(1.9)(0.4841) > 9.85(1.9)(1.5 0.4841) 52.98 > 19.01

    Corte por punzonamiento Vu < Vc

    Vu = Pdin Wnu (m) (n)

    Vu = 35.55 9.85 (0.884)2 = 27.85 Tn

    (0.27)(2 + 4

    ) Vc (0.27)(

    + 2)

    1.1

    0.75(0.27)(2 + 4)210 (10)(1.768)(0.4841) = 150.70 Vc 0.75(0.27) (20)(0.4841)

    1.768 + 2 210 (10)(1.768)(0.4841) = 187.77 0.75 1.1 210 (10)(1.768)(0.4841) = 102.325

  • 21

    Acero

    Mu = 2

    (1)2

    Mu = 9.852

    (1.5)2 (1.9) = 21.05 . = 21.05 105/

    rea del acero

    As =

    (2

    ) = As=()(0.85)()()

    21.051050.9(0.85)(210)(1.90) = 48.41 a 0.5 a2

    0.52 48.41 + 68.963 = 0 = 48.41 48.412 4(0.5)(68.963) 1 = 48.41 46.964

    = . As1= 21.051050.9(4200)(48.41(0.51.446)) = 11.678 2 As2= 1.446(0.85)(210)(190)4200 = 11.676 2 As=11.678 2

    Verificacin de acero mnimo

    As> As 11.678>0.0018 (48.41) (190)

    11.678> 16.556 As =16.556

  • 22

    Nv = 16.556

    2= 8.278 9

    S = 1902(7.5)1.588

    8= 21.67 22 0.22

    Lv =190 2(7.5) = 175 cm = 1.75

    9 @ 0.22

    RESUMEN DE DATOS:

    DATOS Z1 Z2 Z3 Z4

    hs 0.6m 0.6m 0.6m 0.6m

    hz 0.6m 0.6m 0.6m 0.6m

    Lv1=Lv2 1.575m 1.6m 1.55m 1.5m

    d 0.4841m 0.4841m 0.4841m 0.4841m

    Az 13.63m2 7.22m2 6.817m2 3.61m2

    S 3.7m 2.05m 1.949m 1.9m

    T 3.7m 3.6m 3.498m 1.9m

    m 1.034m 0.934m 0.884m 0,884

    n 1.034m 0.934m 0.884m 0,884

    5/8" 5/8" 5/8" 5/8"

    Nv. Long. 17 16 16 9

    Sepr. Long. 0,22 0,24 0,23 0,22

    Nv. Transv. 17 9 9 9

    Sepr. Transv. 0,22 0,24 0,23 0,22