PIP-II 650 MHz β=0.90 & 0.92 Jacketed Cavity Prototype Final …€¦ · Saravan K. Chandrasekaran...
Transcript of PIP-II 650 MHz β=0.90 & 0.92 Jacketed Cavity Prototype Final …€¦ · Saravan K. Chandrasekaran...
In partnership with:
India/DAE
Italy/INFN
UK/STFC
France/CEA/Irfu, CNRS/IN2P3
PIP-II 650 MHz β=0.90 & 0.92 Jacketed Cavity Prototype Final Design Review
Saravan K. Chandrasekaran
PIP-II β=0.90 & 0.92 Jacketed Cavity FDR
1 February 2019
Outline
• Scope/Deliverables
– (Including In-Kind Contributions)
• Requirements
• Interfaces
• Preliminary Design, Maturity
• Technical Progress to Date
• ESH&Q
• Risks and Mitigations
• Summary
2/1/2019S. Chandrasekaran | B90 & B92 JCAV Proto FDR Introduction2
PIP-II Project
2/1/2019S. Chandrasekaran | B90 & B92 JCAV Proto FDR Introduction3
Goals
▪ Deliver 1.2 MW of proton beam power from the Main Injector over
the energy range 60 – 120 GeV, at the start of LBNF ops─ Establish a platform for future upgrades to multi-MW capability
▪ Provide a platform for extension of capability to high duty
factor/higher beam power, multiple users and reliable operations─ Support the ongoing 8 GeV program, including an upgrade path for Mu2e
MissionPIP-II will deliver the world’s most intense beam of neutrinos to the international LBNF/DUNE project, and enable a broad physics research program, powering new discoveries for decades to come.
Building the world’s most powerful neutrino beam
PIP-II SRF & CRYO International Collaborations
2/1/2019S. Chandrasekaran | B90 & B92 JCAV Proto FDR Introduction4
Compressor System
He Gas Tanks
LHeDewar
Cold Box
Distribution Box
Cryogenic Transfer Lines
Gas HeaderHB650HWR SSR1 SSR2 LB650
·
Tex
tCryomodules
HWR X 1 SSR1 X 2
SSR2 X 7
LB650 X 11
HB650 X 4
PIP-II is the first accelerator project in the U.S. with substantial
international participation
PIP-II HB650
2/1/2019S. Chandrasekaran | B90 & B92 JCAV Proto FDR Introduction5
• CW operation & 2 mA beam current
Cryomodule Number (Prototype
+ installed)
Cavity Number
Magnet Number
Testing Note
LB650 1+11 3 0 Partial Test at Partner lab, Full Test at FNAL
Integrated Design
HB650 1+4 6 0 Test at FNAL Integrated Design
PIP-II Project Organization
2/1/2019S. Chandrasekaran | B90 & B92 JCAV Proto FDR Introduction6
650 MHz Technical Team
• 650 MHz Lead: S. Chandrasekaran
• Cavity Q & testing: M. Martinello
• Cavity jacketing & fabrication: C. Grimm
• Cavity design:– RF: I. Gonin, T. Khabiboulline, G. Romanov– Mechanical: I. Gonin, N. Sharma*, V. Jain*, N. Nigam*– Drawings: C. Grimm, V. Jain*
• RF tuning: T. Khabiboulline
• Tuner: Y. Pischalnikov, S. Cheban
• Coupler: N. Solyak, S. Kazakov, O. Pronitchev
• CM design: V. Roger
*Indian Institutions Fermilab Collaboration Guest Engineers
2/1/2019S. Chandrasekaran | B90 & B92 JCAV Proto FDR Introduction7
Review Charge (1)
• Technical Scope– Are the designs mature and technically sound to satisfy design
specifications?– Is the design likely to meet performance expectations?– Have installation issues been adequately addressed?– Have all the major interfaces been identified and incorporated
into the design? – Are all design specifications, requirements, performance, and
interface documents reviewed, approved and released?
• Design Management– Is the design team organized and staffed to successfully
complete the project?– Have all the major risks been identified and managed?– Are procurements appropriately planned?– Is the development of associated drawing packages sufficiently
mature?
2/1/2019S. Chandrasekaran | B90 & B92 JCAV Proto FDR Introduction8
Review Charge (2)
• Cost and Schedule– Is the cost and schedule reasonable to achieve the planned scope?
This is a reasonableness assessment by technical experts, not a detailed cost/schedule review.
• ES&H and QA/QC– Are all related ES&H aspects being properly addressed?– Are appropriate QA and QC steps being implemented?
• Miscellaneous– Have all the previous design review action items/comments been
addressed?– Have lessons learned been addressed?– Are there any other issues that have been identified that need to be
addressed?
• Overall Readiness– Is the design sufficiently mature to allow Final Design Review
approval?
2/1/2019S. Chandrasekaran | B90 & B92 JCAV Proto FDR Introduction9
2/1/201910
END
S. Chandrasekaran | B90 & B92 JCAV Proto FDR Introduction