Status of the FMD

18
Technical Board, 12 July 2005 Børge Svane Nielsen, NBI 1 Status of the FMD Børge Svane Nielsen Niels Bohr Institute

description

Status of the FMD. Børge Svane Nielsen Niels Bohr Institute. Inner prototype status. Leakage current (specs < 3 μ A). Hamamatsu inner sensor prototype: well within specs → No changes for production → Outer sensor design started. 300 nA. IDEAS inner hybrid prototype: - PowerPoint PPT Presentation

Transcript of Status of the FMD

Page 1: Status of the FMD

Technical Board, 12 July 2005 Børge Svane Nielsen, NBI 1

Status of the FMD Status of the FMD

Børge Svane Nielsen

Niels Bohr Institute

Page 2: Status of the FMD

Technical Board, 12 July 2005 Børge Svane Nielsen, NBI 2

Inner prototype statusInner prototype statusLeakage current (specs < 3 μA)

Detector capacitance

300 nA

2 nF

Bias voltage 300 V

Bias voltage300 V

Hamamatsu inner sensor prototype:well within specs

→ No changes for production→ Outer sensor design started

IDEAS inner hybrid prototype: VA1_ALICE chips within specs Minor changes to hybrid details→ 2nd prototype to be delivered mid Aug.

Prototype module (sandwich) status: m.i.p. particles seen (500 MeV e-) Noise level now as expected→ Further beam tests 25-26 July→ 2nd prototype mid Aug.

Readout electronics status: → ongoing

Page 3: Status of the FMD

Technical Board, 12 July 2005 Børge Svane Nielsen, NBI 3

First inner type moduleFirst inner type module

Gluing of first ”sandwich” module and bonding at CERN

500 MeV e- beam test at Aarhus, DK

FMD module

e- beam

hybridsensor pitchadaptor

Page 4: Status of the FMD

Technical Board, 12 July 2005 Børge Svane Nielsen, NBI 4

Aarhus beam testAarhus beam test

Problems discovered: - wrong read-out timing - strip noise too high

Cou

nt

Expected m.i.p.signal

m.i.p.(wrong timing

shifted peak down)

New beam test scheduled 25 July

Recorded energy on single Si strip. Most e- beam outside strip acceptance.

Page 5: Status of the FMD

Technical Board, 12 July 2005 Børge Svane Nielsen, NBI 5

Prototype noise testsPrototype noise tests

Tests to eliminate noise:- bonded ”flat” module (to reduce hybrid-sensor capacitance): no change- various grounding schemes: no change- add noise filter to HV bias: noise reduced to expected value (6-700 ENC)- noise level now independent of further shielding/grounding/power supply/...

Flat module with external HV filter Sandwich module with HV filter on hybrid

Page 6: Status of the FMD

Technical Board, 12 July 2005 Børge Svane Nielsen, NBI 6

Prototype noise testsPrototype noise tests

Short strips(580 ENC)

Long strips(730 ENC)

badchannelson hybrid

unbondedstrips

Page 7: Status of the FMD

Technical Board, 12 July 2005 Børge Svane Nielsen, NBI 7

Further prototype testingFurther prototype testingLab test with sandwich and IDEAS readout

... and Digitizer+RCU readout

Good progress with prototype Digitizer andUSB version of RCUNext:- complete Digitizer+RCU tests- repeat beam tests- build second sandwich with new hybrid RCU Digitizer

Page 8: Status of the FMD

Technical Board, 12 July 2005 Børge Svane Nielsen, NBI 8

FMD internal mechanicsFMD internal mechanics

Support plate:Al honeycomb (?)combined with cooling

Hybrid

Si sensor

space for support feet

Digitizer board

Page 9: Status of the FMD

Technical Board, 12 July 2005 Børge Svane Nielsen, NBI 9

A

A

Cut view A-A

1514

740

SPD cone

53 FMD3

3rd cone

Tensioning device80mm x 12mm

Top corner:Z = 727.5R = 323.4

Bottom corner:Z = 679.4R = 258.4

752

628R

172

R42

R15

4R

284

Wheel centerZ = 469.0R = 60.0

20

134

309

28

R49

2.5

668

45°

R38

4

36

85

26.9

R35

R39

6 (?

)

R40

0

R49

5

3020

45

84985

180

Ring of the temporary supportWings of the temporary support

V0-C

Overall dimensions(Flavio Tosello) RB26

Page 10: Status of the FMD

Technical Board, 12 July 2005 Børge Svane Nielsen, NBI 10

Beam pipe and FMD3 support cone, RB26 side

Beam pipe and FMD3 support cone, RB26 side

Model was modified for integration tests: 4 supports + 4 wheels + wire tensioners

1:1 model usedfor integration tests

Carbon fibre cone designed (NBI+N.Golubev):

Page 11: Status of the FMD

Technical Board, 12 July 2005 Børge Svane Nielsen, NBI 11

Integration test FMD3Integration test FMD3

Page 12: Status of the FMD

Technical Board, 12 July 2005 Børge Svane Nielsen, NBI 12

Finite element calculations of beam pipe support

Finite element calculations of beam pipe support

Displacements below 20 mStresses below 7 MPa(safety factor 20)

Input dataweights: cone 4.82 kg detectors 3kg each (2 detectors)

Load on each string (4 strings): 500 N

But, realistic load is below: 50 N

Carbon fibre structure

Page 13: Status of the FMD

Technical Board, 12 July 2005 Børge Svane Nielsen, NBI 13

A

A

1510

740

1020

R41

5

R54

0

Patch Panel + AirDuct envelope

R49

2.5

752

R15

4R

284

R17

0

shadow of supports of SPD optical connectors

SPD cone

ITS cone

SDD pre-manifold

800 (?)

R28

0

R (

?)

53

R (

?)

834

R17

2R

42

11.6

°

13.1

°

(856?)

RB24

Ring of the temporary supportWings of the temporary support

3020

R40

0

R49

585

180

FMD+pipe support

668

648

78

780

142

Tensioning device26

Overall dimensions(Flavio Tosello)

Page 14: Status of the FMD

Technical Board, 12 July 2005 Børge Svane Nielsen, NBI 14

Preliminary sketch of FMD+beampipe support on RB24(F. Tosello)

60

114

134

1010

142

ITS SIDE

26

ITS

SID

E

60

R492.5

R390

R334

R324

60

10

10

FMD2 supportFMD2 support

Page 15: Status of the FMD

Technical Board, 12 July 2005 Børge Svane Nielsen, NBI 15

FMD2 supportFMD2 supportPreliminary design of FMD+beampipe support on RB24

Page 16: Status of the FMD

Technical Board, 12 July 2005 Børge Svane Nielsen, NBI 16

Integration test FMD2Integration test FMD2

For integration test, a ’quick and heavy’ version of the FMD2 was used.Important dimensions were OK, materials too heavy, FMD protection missing.

Page 17: Status of the FMD

Technical Board, 12 July 2005 Børge Svane Nielsen, NBI 17

FMD3 mechanicsFMD3 mechanics

Support plate

Digitizer boardInternal mechanics asfor FMD2 and FMD3.

Missing a ’frame’ or ’box’to attach to V0.

Needs further interaction with integration team.

Page 18: Status of the FMD

Technical Board, 12 July 2005 Børge Svane Nielsen, NBI 18

ConclusionsConclusions

Inner type sensor (Hamamatsu) and hybrid (IDEAS) work to expectations

→ design of outer sensors started→ ready to order all inner sensors now→ 2nd hybrid prototype in August, small changes

Readout electronics tests with Digitizer and RCU ongoing FMD3 cone: mechanical drawings ready to bring to carbon fibre industry FMD2 support: detailed design to start in August FMD1 box and support: details to be worked out in collaboration with integration team