Status of the FMD
-
Upload
emerson-ball -
Category
Documents
-
view
56 -
download
9
description
Transcript of Status of the FMD
Technical Board, 12 July 2005 Børge Svane Nielsen, NBI 1
Status of the FMD Status of the FMD
Børge Svane Nielsen
Niels Bohr Institute
Technical Board, 12 July 2005 Børge Svane Nielsen, NBI 2
Inner prototype statusInner prototype statusLeakage current (specs < 3 μA)
Detector capacitance
300 nA
2 nF
Bias voltage 300 V
Bias voltage300 V
Hamamatsu inner sensor prototype:well within specs
→ No changes for production→ Outer sensor design started
IDEAS inner hybrid prototype: VA1_ALICE chips within specs Minor changes to hybrid details→ 2nd prototype to be delivered mid Aug.
Prototype module (sandwich) status: m.i.p. particles seen (500 MeV e-) Noise level now as expected→ Further beam tests 25-26 July→ 2nd prototype mid Aug.
Readout electronics status: → ongoing
Technical Board, 12 July 2005 Børge Svane Nielsen, NBI 3
First inner type moduleFirst inner type module
Gluing of first ”sandwich” module and bonding at CERN
500 MeV e- beam test at Aarhus, DK
FMD module
e- beam
hybridsensor pitchadaptor
Technical Board, 12 July 2005 Børge Svane Nielsen, NBI 4
Aarhus beam testAarhus beam test
Problems discovered: - wrong read-out timing - strip noise too high
Cou
nt
Expected m.i.p.signal
m.i.p.(wrong timing
shifted peak down)
New beam test scheduled 25 July
Recorded energy on single Si strip. Most e- beam outside strip acceptance.
Technical Board, 12 July 2005 Børge Svane Nielsen, NBI 5
Prototype noise testsPrototype noise tests
Tests to eliminate noise:- bonded ”flat” module (to reduce hybrid-sensor capacitance): no change- various grounding schemes: no change- add noise filter to HV bias: noise reduced to expected value (6-700 ENC)- noise level now independent of further shielding/grounding/power supply/...
Flat module with external HV filter Sandwich module with HV filter on hybrid
Technical Board, 12 July 2005 Børge Svane Nielsen, NBI 6
Prototype noise testsPrototype noise tests
Short strips(580 ENC)
Long strips(730 ENC)
badchannelson hybrid
unbondedstrips
Technical Board, 12 July 2005 Børge Svane Nielsen, NBI 7
Further prototype testingFurther prototype testingLab test with sandwich and IDEAS readout
... and Digitizer+RCU readout
Good progress with prototype Digitizer andUSB version of RCUNext:- complete Digitizer+RCU tests- repeat beam tests- build second sandwich with new hybrid RCU Digitizer
Technical Board, 12 July 2005 Børge Svane Nielsen, NBI 8
FMD internal mechanicsFMD internal mechanics
Support plate:Al honeycomb (?)combined with cooling
Hybrid
Si sensor
space for support feet
Digitizer board
Technical Board, 12 July 2005 Børge Svane Nielsen, NBI 9
A
A
Cut view A-A
1514
740
SPD cone
53 FMD3
3rd cone
Tensioning device80mm x 12mm
Top corner:Z = 727.5R = 323.4
Bottom corner:Z = 679.4R = 258.4
752
628R
172
R42
R15
4R
284
Wheel centerZ = 469.0R = 60.0
20
134
309
28
R49
2.5
668
45°
R38
4
36
85
26.9
R35
R39
6 (?
)
R40
0
R49
5
3020
45
84985
180
Ring of the temporary supportWings of the temporary support
V0-C
Overall dimensions(Flavio Tosello) RB26
Technical Board, 12 July 2005 Børge Svane Nielsen, NBI 10
Beam pipe and FMD3 support cone, RB26 side
Beam pipe and FMD3 support cone, RB26 side
Model was modified for integration tests: 4 supports + 4 wheels + wire tensioners
1:1 model usedfor integration tests
Carbon fibre cone designed (NBI+N.Golubev):
Technical Board, 12 July 2005 Børge Svane Nielsen, NBI 11
Integration test FMD3Integration test FMD3
Technical Board, 12 July 2005 Børge Svane Nielsen, NBI 12
Finite element calculations of beam pipe support
Finite element calculations of beam pipe support
Displacements below 20 mStresses below 7 MPa(safety factor 20)
Input dataweights: cone 4.82 kg detectors 3kg each (2 detectors)
Load on each string (4 strings): 500 N
But, realistic load is below: 50 N
Carbon fibre structure
Technical Board, 12 July 2005 Børge Svane Nielsen, NBI 13
A
A
1510
740
1020
R41
5
R54
0
Patch Panel + AirDuct envelope
R49
2.5
752
R15
4R
284
R17
0
shadow of supports of SPD optical connectors
SPD cone
ITS cone
SDD pre-manifold
800 (?)
R28
0
R (
?)
53
R (
?)
834
R17
2R
42
11.6
°
13.1
°
(856?)
RB24
Ring of the temporary supportWings of the temporary support
3020
R40
0
R49
585
180
FMD+pipe support
668
648
78
780
142
Tensioning device26
Overall dimensions(Flavio Tosello)
Technical Board, 12 July 2005 Børge Svane Nielsen, NBI 14
Preliminary sketch of FMD+beampipe support on RB24(F. Tosello)
60
114
134
1010
142
ITS SIDE
26
ITS
SID
E
60
R492.5
R390
R334
R324
60
10
10
FMD2 supportFMD2 support
Technical Board, 12 July 2005 Børge Svane Nielsen, NBI 15
FMD2 supportFMD2 supportPreliminary design of FMD+beampipe support on RB24
Technical Board, 12 July 2005 Børge Svane Nielsen, NBI 16
Integration test FMD2Integration test FMD2
For integration test, a ’quick and heavy’ version of the FMD2 was used.Important dimensions were OK, materials too heavy, FMD protection missing.
Technical Board, 12 July 2005 Børge Svane Nielsen, NBI 17
FMD3 mechanicsFMD3 mechanics
Support plate
Digitizer boardInternal mechanics asfor FMD2 and FMD3.
Missing a ’frame’ or ’box’to attach to V0.
Needs further interaction with integration team.
Technical Board, 12 July 2005 Børge Svane Nielsen, NBI 18
ConclusionsConclusions
Inner type sensor (Hamamatsu) and hybrid (IDEAS) work to expectations
→ design of outer sensors started→ ready to order all inner sensors now→ 2nd hybrid prototype in August, small changes
Readout electronics tests with Digitizer and RCU ongoing FMD3 cone: mechanical drawings ready to bring to carbon fibre industry FMD2 support: detailed design to start in August FMD1 box and support: details to be worked out in collaboration with integration team