STATIC AND DYNAMIC IMPACT OF HVDC, TNB-EGAT...
-
Upload
duongtuong -
Category
Documents
-
view
235 -
download
4
Transcript of STATIC AND DYNAMIC IMPACT OF HVDC, TNB-EGAT...
STATIC AND DYNAMIC IMPACT OF HVDC, TNB-EGAT INTERCONNECTION
SYSTEM
SHAHIDA BINTI MOHD SAID @ SAYED
This thesis is submitted as partial fulfillment of the requirements for the award of the
Bachelor of Electrical Engineering (Power Systems)
Faculty of Electrical & Electronics Engineering
University Malaysia Pahang
NOVEMBER, 2010
ii
“All the trademark and copyrights use herein are property of their respective owner.
References of information from other sources are quoted accordingly; otherwise the
information presented in this report is solely work of the author.”
Signature : ____________________________
Author : SHAHIDA BINTI MOHD SAID @ SAYED
Date : 30 NOVEMBER 2010
iv
ACKNOWLEDGEMENT
In the name of ALLAH s.w.t., most gracious, most merciful.
The thesis has been an extremely satisfying experience for me. I would like to
acknowledge all those who have been a part of this project. Firstly, I would like to
express my appreciation to my project supervisor, Mr. Mohd Redzuan Bin Ahmad for
his guidance and advices in pursuing my research idea. Without his continued support
and interest, this thesis cannot be achieved as presented here.
I am also appreciated to my beloved family and friends for their constant on
supporting me to pursue my thesis successfully. Their encouragement and help are very
useful for me on keep doing this project until it successful.
Finally, I would like to thank University Malaysia Pahang (UMP) by giving me
this opportunity to continue my studies here. This opportunity I grab it as my
experiences before go further to the working field.
May God repay all of your kindness.
v
ABSTRACT
HVDC interconnection TNB-EGAT system is the second stage of the grid
interconnection between Malaysia and Thailand. This system is to export the electrical
power during lower demand and import during TNB’s peak load. The objectives of this
project are to study the static and dynamic impacts of HVDC TNB-EGAT system. This
study will also focus on modeling and simulating of the HVDC interconnection system
by using Power System Computer Aided Design (PSCAD/EMTDC) software. The load
flow analysis has been conducted by comparing the simulation from PSCAD with the
actual data. Hence, the fault analysis also has been conducted by locating the fault at the
HVDC modeling which is the DC line fault analysis and AC signal phase short circuit at
inverter station analysis. This system is stabilized by having a transient stability
analysis. The PSCAD software has the features that can be used to conduct such
analysis. This analysis has been performed and the impacts have been monitored on the
system and both power system utilities. From the analysis, some improvements have
been suggested for the future system.
vi
ABSTRAK
HVDC sistem interkoneksi TNB-EGAT merupakan tahap kedua dari
interkoneksi grid antara Malaysia dan Thailand. Sistem ini adalah untuk eksport kuasa
selama permintaan yang lebih rendah dan import selama beban puncak TNB. Tujuan
dari projek ini adalah untuk mempelajari kesan statik dan dinamik sistem HVDC TNB-
EGAT. Penyelidikan ini juga akan mengfokuskan pada pemodelan dan simulasi sistem
interkoneksi HVDC dengan menggunakan Power System Computer Aided Design
(PSCAD/EMTDC) perisian. Analisis aliran kuasa telah dilakukan dengan
membandingkan simulasi dari PSCAD dengan data aktual. Oleh sebab itu, analisis
kesalahan juga telah dilakukan dengan meletakkan kesalahan pada pemodelan HVDC
yang merupakan garis analisis kesalahan DC dan isyarat AC rangkaian fasa pendek pada
analisis stesen inverter. Sistem ini akan stabil dengan memiliki analisis kestabilan
transien. Perisisan PSCAD mempunyai ciri-ciri yang boleh digunakan untuk melakukan
analisis tersebut. Analisis ini telah dilakukan dan kesannya telah dipantau pada sistem
dan utiliti sistem kuasa untuk keduanya. Dari analisis tersebut, beberapa pembaikan
telah dicadangkan untuk sistem pada masa hadapan.
vii
TABLE OF CONTENTS
CHAPTER CONTENTS PAGE
TITLE i
DECLARATION ii
DEDICATION iii
ACKNOWLEDGEMENT iv
ABSTRACT v
ABSTRAK vi
TABLE OF CONTENTS vii
LIST OF TABLES x
LIST OF FIGURES xi
LIST OF SYMBOLS xiii
LIST OF ABREVIATIONS xiv
LIST OF APPENDICES xv
1 INTRODUCTION
1.1. Overview of The Project 1
1.2. Objective 3
1.3. Scope of Project 3
1.4. Problem Statement 3
1.5. Literature Review 4
1.6. Thesis Outline 5
viii
2 HIGH VOLTAGE DIRECT CURRENT (HVDC) TNB-EGAT
INTERCONNECTION SYSTEM
2.1. Introduction 8
2.2. Operation of HVDC 10
2.3. HVDC System Configuration 12
2.4. HVDC Converter Station 15
2.5. Differences of HVDC and HVAC 15
2.6. Advantages of HVDC 16
2.7. Application of HVDC 17
2.8. TNB Side 18
2.9. EGAT Side 19
2.10. HVDC Controls 20
2.11. Summary 22
3 STATIC AND DYNAMIC IMPACT OF HVDC
INTERCONNECTION SYSTEM
3.1. Introduction 23
3.2. Static and Dynamic Impacts 24
3.3. Tools 25
3.4. Analysis Procedures 27
3.5. Modelling of HVDC System 30
3.6. Calculation of the Parameters 36
3.7. Summary 45
4 RESULTS AND DISCUSSIONS
4.1. Introduction 46
4.2. Simulation in PSCAD/EMTDC 47
4.2.1. Load Flow Analysis 50
4.2.2. Fault Analysis 55
4.3. Summary 64
ix
5 CONCLUSIONS AND RECOMMENDATIONS
5.1. Conclusions 65
5.2. Recommendations 67
REFERENCES 68
APPENDIXES 71
x
LIST OF TABLES
TABLE NO. TITLE PAGE
3.1 AC Equivalent Circuits Parameters of TNB-EGAT 31
HVDC Network
3.2 Parameters of Triple Tuned Filter at Rectifier AC Network 32
3.3 Parameters of Triple Tuned Filter at Inverter AC Network 33
3.4 PI Controller Parameter of Rectifier Current Controller 35
3.5 VDCOL Controller Parameter of Rectifier Current Controller 36
3.6 PI Controller Parameter for Inverter Current Controller and CEA
Controller 36
xi
LIST OF FIGURES
FIGURE NO. TITLE PAGE
2.1 TNB-EGAT AC-HVDC Network Schematic Overview 10
2.2 Simplified AC-HVDC Systems Diagram 11
2.3 Monopolar Link 12
2.4 Bipolar Link 13
2.5 Back To Back Link 14
2.6 Parallel Multiterminal System 14
2.7 Series Multiterminal Link 14
2.8 TNB Side AC-HVDC Network 19
2.9 EGAT Side AC-HVDC Network 19
2.10 Simple DC Current Controller 20
2.11 Simple Extinction Angle Controller 21
3.1 Overview of PSCAD/EMTDC Model for TNB-EGAT
Network 27
3.2 Flowchart of the Project 29
3.3 TNB-EGAT AC System Equivalents Circuit 30
3.4 Triple Tuned Filter at Rectifier AC Network 31
3.5 Triple Tuned Filter at Inverter AC Network 32
3.6 Capacitor Bank at Rectifier Side 33
3.7 Capacitor Bank at Inverter Side 34
3.8 Passive DC Filter Installation at DC Transmission Line 34
3.9 AC Current Flow Diagram 43
4.1 Overall Overview of HVDC Interconnection System 47
xi
4.2 Rectifier Circuit 48
4.3 Rectifier Current Control 48
4.4 Inverter Circuit 49
4.5 Inverter Current Control 49
4.6 Graph at Rectifier Side 50
4.7 Results at Rectifier Side as in Meter 51
4.8 Graph at Inverter Side 52
4.9 Results at Inverter Side as in Meter 52
4.10 The Effect of Iorder 53
4.11 Power Meter at Rectifier Side and Inverter Side 54
4.12 Fault Simulation Model 55
4.13 Overall Overview of DC Line Short Circuit Fault 56
4.14 Graph of AC Volts (RMS) with DC Fault at Rectifier Side 57
4.15 Graph of DC Volts and DC Current at Rectifier Side 57
4.16 Power Meter at Rectifier Side 58
4.17 Graph of AC Volts (RMS) with DC Fault at Inverter Side 58
4.18 Graph of DC Volts and DC Current at Inverter Side 59
4.19 Power Meter at Inverter Side 59
4.20 DC Line Short Circuit of IEEE Paper 60
4.21 Overall Overview of AC Signal Phase Short Circuit at
Inverter Station 60
4.22 Graph of AC Volts (RMS) with AC Signal Phase Short
Circuit at Rectifier Side 61
4.23 Graph of DC Volts and DC Current at Rectifier Side 61
4.24 Power Meter at Rectifier Side 62
4.25 Graph of AC Volts (RMS) with AC Signal Phase Short
Circuit at Rectifier Side 62
4.26 Graph of DC Volts and DC Current at Inverter Side 63
4.27 Power Meter at Inverter Side 63
4.28 AC Signal Phase Short Circuit at Inverter Station of IEEE
Paper 64
xiii
LIST OF SYMBOLS
p.u - Per Unit
V - Voltage
P - Active Power
Q - Reactive Power
S - Apparent Power
W - Wattage
Var - Varians
IOrder - DC Current Order
α - Valve Ignition Delay Angle
- Commutation Margin Angle
xiv
LIST OF ABBREVIATIONS
PSCAD - Power System Computer Aided Design
EMTDC - Electromagnetic Transient
HVDC - High Voltage Direct Current
HVAC - High Voltage Alternating Current
DC - Direct Current
AC - Alternating Current
TNB - Tenaga Nasional Berhad
EGAT - Electricity Generating Authority of Thailand
PI - Proportional Integral
RMS - Root Mean Square
VDCOL - Voltage Dependent Current Order Limiter
CEA - Constant Extinction Angle
xv
LIST OF APPENDICES
APPENDIX TITLE PAGE
A Flow Chart 71
B Data 73
C Gantt Chart 82
CHAPTER 1
INTRODUCTION
1.1. Overview of The Project
As early as 1881 Mercel Deprez, inspired by experiments with arc lights across
a DC generator, published the first theoretical examination of HVDC power
transmission. He soon put theory into practice and by 1882 he transmitted 1.4 kW at 2
kV over a distance of 35 miles. Electric power transmission was originally developed
with direct current. The availability of transformers and the development and
improvement of induction motors at the beginning of the 20th Century, led to greater
appeal and use of A.C. transmission. Through research and development in Sweden at
Allmana Svenska Electriska Aktiebolaget (ASEA), an improved multi-electrode grid
controlled mercury arc valve for high powers and voltages was developed from 1929.
Experimental plants were set up in the 1930’s in Sweden and the USA to investigate the
use of mercury arc valves in conversion processes for transmission and frequency
changing. D.C. transmission now became practical when long distances were to be
covered or where cables were required. The increase in need for electricity after the
Second World War stimulated research, particularly in Sweden and in Russia. In 1950, a
2
116 km experimental transmission line was commissioned from Moscow to Kasira at
200 kV. The first commercial HVDC line built in 1954 was a 98 km submarine cable
with ground return between the island of Gotland and the Swedish mainland. In power
transmission system, High Voltage Direct Current (HVDC) is used widely in most of
modern countries. HVDC is used in transmission system for long distances. When
HVDC is combined in AC power system, there are many impacts occurs inside the
system such as static and dynamic impacts.
This project is to study the static and dynamic impact of HVDC, TNB-EGAT
interconnection system in order to upgrade their system in power transmission system if
the fault occurred. The analysis of this project is fully using the Power System
Computer Aided Design (PSCAD) program. The static impacts of this project are load
flow analysis and fault analysis. Moreover, the dynamic impact of this project is
transient stability analysis.
The HVDC network is based on the actual of TNB-EGAT project. The
simulation model consists of a static AC equivalent circuit, converter transformer,
converter valve group, DC transmission line, converter controllers, DC filter and AC
filters. The parameters of equivalent AC networks, HVDC converters, DC link, filters
and etc. are modelled through the PSCAD/EMTDC program.
3
1.2. Objective
The objective of this project is to study the static and dynamic impact of HVDC,
TNB-EGAT interconnection system. Hence, to conduct the load flow analysis, fault
analysis and transient stability analysis of the system. Beside that, the objective is to
model and simulate the HVDC interconnection system by using Power System
Computer Aided Design (PSCAD)/EMTDC program.
1.3. Scope of The Project
The scopes of this project focus on modeling and simulating HVDC
interconnection for TNB-EGAT system. This project has been modeled by referring the
actual system of TNB-EGAT. Moreover, this project is focused on conducting the load
flow analysis and fault analysis.
1.4. Problem Statement
From this project, there is having three problem statements. The first one is
study of the static impacts that are important in order to planning, economic scheduling
and control of an existing system as well as planning its future expansion. Its also
provide with safety purpose too. The second one is study of dynamic impacts are
important in order to maintain in stability after large, major and sudden disturbance.
The third one understands the HVDC system.
4
1.5. Literature Review
Power systems around the world are experiencing continuous unprecedented
change and stress due to increasing consumer load coupled with environmental and
resource constraints. These problems have been alleviated to some extent by using
HVDC transmission links [1]. High Voltage Direct Current (HVDC) transmission is
widely recognized as being advantageous for long-distance, bulk power delivery,
asynchronous interconnections and long submarine cable crossings. HVDC lines and
cables are less expensive and have lower losses than those for three-phase AC
transmission [2].
The 300 MW Thailand-Malaysia HVDC interconnection systems consist
of Khlong Ngae converter station on the Thai border and Gurun converter station on the
Malaysia border. Both stations are linked by a 300 kV DC overhead transmission line of
110 km. EGAT’s Khlong Ngae converter station is situated at Sadao district in
Southern Songkhla province, about 24 km from Thai-Malaysia border. TNB’s Gurun
converter station is located in Kedah, about 86 km from Malaysia’s northern border [14].
A contract was signed between TNB and EGAT on 15 August 1997 for the development
of the Malaysia-Thailand 300/600 MW HVDC Interconnection Project, to serve the
following purposes which are sharing of spinning reserve between TNB and EGAT AC
system, to take advantage of a more economical power exchange between both countries
due to the different daily peak consumption periods, emergency assistance to either AC
network and reactive power support (voltage control) to both AC networks [5].
In this project, there are having three analyses which are load flow analysis,
fault analysis and transient stability analysis. These analyses are modeled in PSCAD
program. PSCAD/EMTDC is a general-purpose time domain simulation program for
simulating power systems electromagnetic transients and its controls. The modelling is
5
referring to the CIGRE Benchmark with the actual parameter of data from TNB. The
CIGRE HVDC Benchmark test model is used as the test system [1].
HVDC transmission applications can be broken down into different basic
categories. Although the rationale for selection of HVDC is often economic, there may
be other reasons for its selection. HVDC may be the only feasible way to interconnect
two asynchronous networks, reduce fault currents, utilize long cable circuits, bypass
network congestion, share utility rights-of-way without degradation of reliability and to
mitigate environmental concerns. In all of these applications, HVDC nicely
complements the AC transmission system [6].
1.6. Thesis Outline
This thesis includes five chapters. The brief outline of each chapter is presented
as below:
i. Chapter 1
This Chapter 1 is an introduction which is the overview of the project,
objective of the project, scope of the project description, problem
statement regarding to this research and the literature reviews that
previous works done by researchers.
6
ii. Chapter 2
This Chapter 2 is the detail explanation about the project which is about
high voltage direct current (HVDC) that are includes the introduction,
operation of HVDC, HVDC system configuration, HVDC converter
station, differences of HVDC and HVAC, advantages of HVDC,
application of HVDC, TNB side, EGAT side and the HVDC controls.
iii. Chapter 3
This Chapter 3 is about the details of static and dynamic impact of
HVDC interconnection system which includes with introduction and the
static and dynamics impact of the system. In this chapter is the analysis
of the project that will discuss about what tools that are being used and
what is the parameter are needed in circuit diagram of TNB-EGAT AC-
HVDC network and the methodology by doing this project.
iv. Chapter 4
This Chapter 4 will discuss about the result that will achieve at the end
of this project by doing the simulation of PSCAD. These results will be
achieved by doing these analyses which are load flow analysis and fault
analysis that is having a different type of fault.
7
v. Chapter 5
The last chapter is Chapter 5 which contains of the conclusion of overall
project by state the final result that gained from the project. The future
recommendations also stated in order to improve this project in the
future undertakings.
CHAPTER 2
HIGH VOLTAGE DIRECT CURRENT (HVDC) TNB-EGAT INTERCONNECTION
SYSTEM
2.1. Introduction
High voltage is used for transmission to reduce the energy lost in the resistance
of the wires. Power in a circuit is proportional to the current but the power loss as heat
in the wires is proportional to the square of the current. However, power is also
proportional to voltage, so for a given power level, higher voltage can be traded off for
lower current. Thus, the higher voltage can be produced the lower of the power loss.
Power loss can also be reduced by reducing resistance. Commonly achieved by
increasing the diameter of the conductor, but larger conductors are heavier and more
expensive.
High Voltage Direct Current (HVDC) technology has characteristics which
makes it especially attractive for certain transmission applications. HVDC transmission
is widely recognized as being advantageous for long-distance, bulk power delivery,
asynchronous interconnections and long submarine cable crossings. The number of
9
HVDC projects committed or under consideration globally have increased in recent
years reflecting a renewed interest in this mature technology. New converter designs
have broadened the potential range of HVDC transmission to include applications for
underground, offshore, economic replacement of reliability-must-run generation, and
voltage stabilization. Developments include higher transmission voltages up to ±800
kV, capacitor-commutated converters (CCC) for weak system applications and voltage-
sourced converters (VSC) with dynamic reactive power control. This broader
technology range has increased the potential HVDC applications and contributed to the
recent growth of HVDC transmission. HVDC transmission applications can be broken
down into different basic categories. Although the rationale for selection of HVDC is
often economic, there may be other reasons for its selection. HVDC may be the only
feasible way to interconnect two asynchronous networks, reduce faults, currents, utilize
long cable circuits, bypass network congestion, share utility rights-of-way without
degradation of reliability and to mitigate environmental concerns. In all of these
applications, HVDC nicely complements the AC transmission system.
The interconnection between TNB and EGAT consists of the construction of a
110 km HVDC line (86 km TNB, 24 km EGAT) with DC converter stations (12-pulse)
at both ends. The interconnection will be between Gurun 500/275 kV (50Hz) substation
on the Malaysia side and Khlong Ngae 230 kV (50Hz) substation on the Thailand side.
The converter station at Gurun will be constructed for bi-directional 300 MW monopolar
operations. In the past, the AC transmission line system linked between Thailand and
Malaysia to exchange the energy power with the capacity of 80 MW transferred from
Sadao Substation in Thailand. At the present, the HVDC grid network is implemented
for connection of the asynchronous 230 kV AC system of Thailand with 275 kV AC
system of Malaysia. The capacity of HVDC interconnection between Thailand and
Malaysia is 300 MW with the maximum overload capacity of 450 MW for 10 minutes.
The 110 km DC overhead transmission line is connected at voltage level of 300 kV
(approximately 24 km from the Thailand border and 86 km from Malaysia border).
10
Initially, the converter station is configured as a monopole converter of 300
MW. Provision has also been made for adding a second 300 MW pole in the future in
order to extend the system into a bipolar configuration with a total capacity of 600 MW.
The first objective of this connection is to provide various benefits of both countries
comprising such as economic exchange of power between two different networks,
enhancing system reliability, sharing spinning reserve, sharing experiences on HVDC
operation and maintenance system to extend closer cooperation between Thailand and
Malaysia. Figure 2.1 below is illustrated as TNB-EGAT AC-HVDC network schematic
overview.
Figure 2.1: TNB-EGAT AC-HVDC Network Schematic Overview
2.2. Operation of HVDC
The power system is begin from power plant which is the electrical power is
producing by generator. The generator can be operated by using steam from many
sources like winding, nuclear, gas and coal. From power plant, electrical power will be