Alternative form with detuning factor F. Quiz: SIMC PI-tunings (a) The Figure shows the response (y)...
-
Upload
rodger-stephens -
Category
Documents
-
view
219 -
download
0
Transcript of Alternative form with detuning factor F. Quiz: SIMC PI-tunings (a) The Figure shows the response (y)...
Quiz: SIMC PI-tunings
(a) The Figure shows the response (y) from a test where we made a step change in the input (Δu = 0.1) at t=0. Suggest PI-tunings for (1) τc=2,. (2) τc=10.
t [s]
y
Step response
y
Time t
SIMC-tunings
(b) Do the same, given that the actual plant is
QUIZ
OUTPUT y INPUT uTunings from Step response “by eye” modelSetpoint change at t=0, input disturbance = 0.1 at t=50
Tunings from Half rule (Somewhat better)
Kc=9.5, tauI=10
Kc=2.9, tauI=10
Kc=2, tauI=5.5
Kc=6, tauI=5.5
SIMC-tunings
Some discussion points
Selection of τc: some other issues Obtaining the model from step responses: How
long should we run the experiment? Cascade control: Tuning Controllability implications of tuning rules
Selection of c: Other issues Input saturation.
Problem. Input may “overshoot” if we “speedup” the response too much (here “speedup” = /c).
Solution: To avoid input saturation, we must obey max “speedup”:
A little more on obtaining the model from step response experiments “Factor 5 rule”: Only dynamics
within a factor 5 from “control time scale” (c) are important
Integrating process (1 = 1)Time constant 1 is not important if it is much larger
than the desired response time c. More precisely, may use
1 =1 for 1 > 5 c
Delay-free process (=0)Delay is not important if it is much smaller than the
desired response time c. More precisely, may use
¼ 0 for < c/5
0 10 20 30 40 50 600.9949
0.995
0.995
0.9951
0.9951
0.9952
0.9952
0.9953
0.9953
0.9954
¼ 1(may be neglected for c > 5)
1 ¼ 200(may be neglected for c < 40)
time
c = desired response time
Step response experiment: How long do we need to wait? RULE: May stop at about 10 times effective delay
FAST TUNING DESIRED (“tight control”, c = ): NORMALLY NO NEED TO RUN THE STEP EXPERIMENT FOR LONGER THAN ABOUT 10 TIMES THE EFFECTIVE DELAY () EXCEPTION: LET IT RUN A LITTLE LONGER IF YOU SEE THAT IT IS ALMOST SETTLING (TO GET 1 RIGHT)
SIMC RULE: = min (, 4(c+)) with c = for tight control
SLOW TUNING DESIRED (“smooth control”, c > ):
HERE YOU MAY WANT TO WAIT LONGER TO GET 1 RIGHT BECAUSE IT MAY AFFECT THE INTEGRAL TIME BUT THEN ON THE OTHER HAND, GETTING THE RIGHT INTEGRAL TIME IS NOT ESSENTIAL FOR SLOW TUNING SO ALSO HERE YOU MAY STOP AT 10 TIMES THE EFFECTIVE DELAY ()
“Integrating process” (c < 0.2 1): Need only two parameters: k’ and From step response:
0 2 4 6 8 102.1
2.2
2.3
2.4
2.5
2.6
2.7
2.8Response on stage 70 to step in L
7.5 min
2.62-2.19
Example.
Step change in u: u = 0.1Initial value for y: y(0) = 2.19Observed delay: = 2.5 minAt T=10 min: y(T)=2.62Initial slope:
y(t)
t [min]
Example (from quiz)
Assume integrating process, theta=1.5; k’ = 0.03/(0.1*11.5)=0.026 SIMC-tunings tauc=2: Kc=11, tauI=14 (OK) SIMC-tunings tauc=10: Kc=3.3, tauI = 46 (too long because process is not actually
integrating on this time scale!)
tauc=2
tauc=10
OUTPUT y INPUT y
Step responseΔu=0.1
Cascade control
CC
TCTs
xB
CC: Primary controller (“slow”): y1 = xB (“original” CV), u1 = y2s (MV)TC: Secondary controller (“fast”): y2 = T (CV), u2 = V (“original” MV)
Tuning: 1. First tune TC (based on response from V to T)2. Close TC and tune CC(based on response from Ts to xB)
Primary controller (CC)sets setpoint to secondary controller (TC).
Cascade control
Tuning of cascade controllers
See next slide
Cascade control
• Want to control y1 (primary CV), but have “extra” measurement y2• Idea: Secondary variable (y2) may be tightly controlled and this
helps control of y1.• Implemented using cascade control: Input (MV) of “primary”
controller (1) is setpoint (SP) for “secondary” controller (2)• Tuning simple: Start with inner secondary loops (fast) and move
upwards• Must usually identify ”new” model ( G1’ = G1 G21 K2 (I+K2G22)-1 )
experimentally after closing each loop
• One exception: Serial process, G21 = G22 2– Inner (secondary-2) loop may be modelled with gain=1 and effective
delay=(c+
Special case: Serial cascade
K2 is designed based on G2 (which has effective delay 2)
then y2 = T2 r2 + S2 d2 where S2 ¼ 0 and T2 ¼1 · e-(2+c2)s
T2: gain = 1 and effective delay = 2+c2
NOTE: If delay is in meas. of y2 (and not in G2) then T2 ¼ 1 ·e-c2s
SIMC-rule: c2 ≥ 2
Time scale separation: c2 ≤ c1/5 (approximately)
K1 is designed based on G1’ = G1T2
same as G1 but with an additional delay 2+c2
y2 = T2 r2 + S2d2, T2 = G2K2(I+G2K2)-1
Cascade control
Example: Cascade control serial process d=6
Without cascade
With cascade
G1u
y1
K1
ys G2K2
y2y2s
Use SIMC-rules!
Cascade control
Tuning cascade control: serial process Inner fast (secondary) loop:
P or PI-control Local disturbance rejection Much smaller effective delay (0.2 s)
Outer slower primary loop: Reduced effective delay (2 s instead of 6 s)
Time scale separation Inner loop can be modelled as gain=1 + 2*effective delay (0.4s)
Very effective for control of large-scale systems
Cascade control
py
pt
y sy
t0t
uy
sy
Procedure:• Switch to P-only mode and make
setpoint change• Adjust controller gain to get overshoot
about 0.30 (30%)
Record “key parameters”:1. Controller gain Kc0
2. Overshoot = (Δyp-Δy∞)/Δy∞
3. Time to reach peak (overshoot), tp
4. Steady state change, b = Δy∞/Δys. Estimate of Δy∞ without waiting to settle:
Δy∞ = 0.45(Δyp + Δyu) Advantages compared to Ziegler-Nichols:* Not at limit to instability * Works on a simple second-order process.
Alternative closed-loop approach:Setpoint overshoot method
Closed-loop step setpoint response with P-only control.
Setpoint overshoot method
M. Shamsuzzoha and S. Skogestad, ``The setpoint overshoot method: A simple and fast method for closed-loop PID tuning'',Journal of Process Control, 20, xxx-xxx (2010)
Choice of detuning factor F: F=1. Good tradeoff between “fast and robust” (SIMC with τc=θ) F>1: Smoother control with more robustness F<1 to speed up the closed-loop response.
pI pτ =min 0.86A ,b
t t1-b
2.44
F
From P-control setpoint experiment record “key parameters”:1. Controller gain Kc0
2. Overshoot = (Δyp-Δy∞)/Δy∞
3. Time to reach peak (overshoot), tp
4. Steady state change, b = Δy∞/Δys
Summary setpoint overshoot method
0c cK = K A F2A= 1.152( ) - 1.6overshoot overs07( ) + 1.0hoot
Proposed PI settings (including detuning factor F)
Setpoint overshoot method
1
1 0.2 1 0.04 1 0.008 1g
s s s s
0 5 10 15 200
0.25
0.5
0.75
1
1.25
time
OU
TP
UT
y
Proposed method with F=1 (overshoot=0.104)Proposed method with F=1 (overshoot=0.292)Proposed method with F=1 (overshoot=0.598)SIMC (
c=
effective=0.148)
Example: High-order process
P-setpoint experiments
Closed-loop PI response
Setpoint overshoot method
5 1
seg
s
First-order unstable process
0 20 40 60 800
0.5
1
1.5
2
time
OU
TP
UT
y
Proposed method with F=1 (overshoot=0.10)Proposed method with F=1 (overshoot=0.30)Proposed method with F=1 (overshoot=0.607)
Example: Unstable plant
• No SIMC settings available
Closed-loop PI response
Setpoint overshoot method
A comment on Controllability (Input-Output) “Controllability” is the ability to
achieve acceptable control performance (with any controller)
“Controllability” is a property of the process itself Analyze controllability by looking at model G(s) What limits controllability?
CONTROLLABILITY
Recall SIMC tuning rules
1. Tight control: Select c= corresponding to
2. Smooth control. Select Kc ¸
Must require Kc,max > Kc.min for controllability
)
Controllability
initial effect of “input” disturbance
max. output deviation
y reaches k’ ¢ |d0|¢ t after time ty reaches ymax after t= |ymax|/ k’ ¢ |d0|
CONTROLLABILITY
ControllabilityCONTROLLABILITY
• More general disturbances. Requirement becomes (for c=):
• Conclusion: The main factors limiting controllability are – large effective delay from u to y ( large)– large disturbances (k’d |d0| / ymax large)
• Can generalize using “frequency domain”: |Gd(j¢0.5/max)| ¢|d0| = |ymax|
Following step disturbance d0:Time it takes for output yto reach max. deviation
Example: Distillation column
CONTROLLABILITY
0 1 2 3 4 5 6 7 8 9 10-2
0
2
4
6
8
10
12
14
16x 10
-3
time [min]
Response to 20% increase in feed rate (disturbance) with no control
xB(t)
xD(t)
ymax=0.005
time to exceed bound = ymax/k’d |d| = 3 min
Controllability: Must close a loop with time constant (c) faster than 1.5 min toavoid that bottom composition xB exceeds max. deviationIf this is not possible: May add tank (feed tank?, larger reboiler volume?) to smooth disturbances
Data for “column A”Product purities:xD = 0.99 § 0.002, xB=0.01 § 0.005(mole fraction light component)Small reboiler holdup, MB/F = 0.5 min
Max. delay in feedbackloop, max = 3/2 = 1.5 min
Example: Distillation column
CONTROLLABILITY
0 1 2 3 4 5 6 7 8 9 10-2
0
2
4
6
8
10
12
14
16x 10
-3
0 1 2 3 4 5 6 7 8 9 10-2
0
2
4
6
8
10
12
14
16x 10
-3
time [min]
Increase reboiler holdup to MB/F = 10 min
xB(t)
3 min 5.8 min
xB(t)
Original holdup Larger holdup
With increased holdup: Max. delay in feedback loop: = 2.9 min
Conclusion controllability If the plant is not controllable then improved
tuning will not help Alternatives
1. Change the process design to make it more controllable Better “self-regulation” with respect to disturbances, e.g.
insulate your house to make y=Tin less sensitive to d=Tout.
2. Give up some of your performance requirements
CONTROLLABILITY