HBDHV Status Update

Jason

for the HBD crew

Jan 30, 2007

Page 2: 1 HBD HV Status Update Jason for the HBD crew Jan 30, 2007.

WEST EAST

2

1

3

0

5

4

NORTH NORTHSOUTH SOUTH

26 Jan 2007Bertan Status

T : ----------------M: ----------------B : ----------------

T:~4μA @500VM: ----------------B : ----------------

T:~8μA @500VM: ----------------B : ----------------

T : ----------------M: ----------------B : ----------------

T:~4μA @500VM: ----------------B : ----------------

T:~7μA @534VM: ----------------B : ----------------

T:~15μA @520VM: ----------------B : ----------------

T : ----------------M: ----------------B : ----------------

T:~11μA @537VM: ----------------B : ----------------

T:410nA @535VM: ----------------B : ----------------

T:~12μA @524VM: ----------------B:~26μA @520V

T:~20μA @529VM: ----------------B : ----------------

T : ----------------M: ----------------B:~26μA @550V

T:~23μA @520VM: ----------------B : ----------------

T:~11μA @430VM: dead 20MΩB : ----------------

T : ----------------M: dead 20MΩB : ----------------

T : ----------------M: dead 20MΩB:~9μA @550V

T:~24μA @550VM: ----------------B : ----------------

T:~22μA @550VM: ----------------B : ----------------

T:~37μA @500VM: ----------------B : ----------------

T:700nA @500VM: ----------------B : ----------------

T : ----------------M: dead 20MΩB : ----------------

inf resistance 20MΩ

T:540nA @500VM:76μA @500VB:51μA @520V

T : ----------------M:~46μA @300VB : ----------------

Page 3: 1 HBD HV Status Update Jason for the HBD crew Jan 30, 2007.

30 Jan 2007LeCroy Status

more-or-less consistentwith Bertan tests…

exceptions:• WN0, draws less current

• inf res on 13.5M short• WS2, draws less current

• 20M on mid (dead?)• 10M on 60M short

• ES4, draws more current• 20M on 25M short

Many GEMs seem to improveover time.

WS3, EN2 draw high current and trip. EN0 has a bad cable (maybe?)

Page 4: 1 HBD HV Status Update Jason for the HBD crew Jan 30, 2007.

4

Status as of Jan. 26, 2007

TOP MID BOT

There are problems in 25 GEMs (out of 72):• 16 top • 5 middle • 4 bottom

Top GEMs… • are Au (not Cu)• thin (~300nm) CsI layer• only GEM truly exposed to HBD volume• only GEM touching the mesh’s frame• ???

Page 5: 1 HBD HV Status Update Jason for the HBD crew Jan 30, 2007.

T M B

5

Examples of Various GEM Behavior

3 draw low current (410, 510, 777nA) at ~500V reflecting a very high GEM impedance (0.6 – 1.3 G).

9 draw high current (ranging from 3 – 15A at about ~500V) reflecting a GEM impedance of 16 – 140M.

10 have a dead (or almost dead) short and the 10M has been replaced by a 20.

4 seem to have multi-strip problems and the 10M has been removed.

47 draw < 1nA on the way up to 520V.

T M B

T M B

T M B

Page 6: 1 HBD HV Status Update Jason for the HBD crew Jan 30, 2007.

6

Summary

• 25 of 72 GEMs have troubles of some kind

• most (16) are top GEMs

• Uniform distribution of problems is scary…

• GEMs showing >20M could still be more than 1 strip!

• 5 of 24 working modules (drawing appropriate current)

• 2 of these have “dead 20M” shorts (resistors replaced)

• Tentative plan for the run:

• frequent MIP peak scans (calibrations)

• swap out resistors (as needed) every access (every 2 weeks?).

Page 7: 1 HBD HV Status Update Jason for the HBD crew Jan 30, 2007.

EN012

EN0 EN1 EN2

TOP

MID

BOT

Page 8: 1 HBD HV Status Update Jason for the HBD crew Jan 30, 2007.

EN345

EN3 EN4 EN5

TOP

MID

BOT

Page 9: 1 HBD HV Status Update Jason for the HBD crew Jan 30, 2007.

ES012

ES0 ES1 ES2

TOP

MID

BOT

Page 10: 1 HBD HV Status Update Jason for the HBD crew Jan 30, 2007.

EN345

ES3 ES4 ES5

TOP

MID

BOT

Page 11: 1 HBD HV Status Update Jason for the HBD crew Jan 30, 2007.

WN012

WN0 WN1 WN2

TOP

MID

BOT

Page 12: 1 HBD HV Status Update Jason for the HBD crew Jan 30, 2007.

WN345

WN3 WN4 WN5

TOP

MID

BOT

Page 13: 1 HBD HV Status Update Jason for the HBD crew Jan 30, 2007.

WS012

WS0 WS1 WS2

TOP

MID

BOT

Page 14: 1 HBD HV Status Update Jason for the HBD crew Jan 30, 2007.

WS345

WS3 WS4 WS5

TOP

MID

BOT

Page 15: 1 HBD HV Status Update Jason for the HBD crew Jan 30, 2007.

TOP MID BOT TOP MID BOT

TOP MID BOT TOP MID BOT

3 draw low current (410, 510, 777nA) at ~500V reflecting a very high GEM impedance (0.6 – 1.3 G).

9 draw high current (ranging from 3 – 15A at about ~500V) reflecting a GEM impedance of 16 – 140M.

10 have a dead (or almost dead) short and the 10M has been replaced by a 20.

4 seem to have multi-strip problems and the 10M has been removed.