Inspection Test Plan (ITP)

for Pipeline Construction

& Project Quality Management

Alexandros ChoremiotisTechnical Director

Via G. Corti 5, Balerna, Switzerland. Contact: [email protected]

Page 2: Inspection Test Plan (ITP) for Pipeline Construction ...

- Inspection & Certification Body

- Accredited Company which operates Internationally in the fields of Industrial Inspection and Certification.

- Our organization provides Inspection & Certification Services in the following main categories:

❖Management Systems Certification – ISO 17021 Accredited

❖Third Party Inspection, Monitoring and Approval – ISO 17020 Accredited

❖Personnel Certification – ISO 17024 Accredited

❖Product Certification – ISO 17065 Accredited

SWISS APPROVAL INTERNATIONAL

Via G. Corti 5, Balerna, Switzerland. Contact: [email protected]

Page 3: Inspection Test Plan (ITP) for Pipeline Construction ...

Notification Body Services (No.Bo. 2221) –European Directives recognized Body

Swiss Approval is a Notified Body 2221, for the following European Directives:

- Pressure Equipment Directive (PED), 2014/68/EU (Vessels, Piping & Unit Certification According Module G inspected & approved by Swiss Approval)

- Lifts Directive, 2014/33/EU: As a Notified Body, Swiss Approval has certified over 6000 elevators in many countries, and more than 3000 retests have been implemented according to National legislations

- Simple pressure Vessel Directive (SPVD), 2014/29/EU: Swiss Approval is Notified Body 2221, having inspected and approved a wide range of welded vessels, on behalf of more than 300 different constructors worldwide.

- Construction Product Regulation, 305/2011/EU,

- Machinery Directive, 2006/42/EC, The certification of Construction Products & Machinery Equipment, is one of our important activities Internationally.

Via G. Corti 5, Balerna, Switzerland. Contact: [email protected]

SWISS APPROVAL INTERNATIONAL

Page 4: Inspection Test Plan (ITP) for Pipeline Construction ...

Personnel Certification – ISO 17024 Accredited

Swiss Approval International offers innovative, specialized training programsand certifications, recognized by major Welding Institutes and InspectionBodies, accepted by the international market.

▪ QA/QC Welding Coordinator

▪ Specialist Welding Inspector

▪ Specialist Welding Inspector in Marine Section

▪ Witness & Manufacturing Welding Inspector

▪ Welders according to EN ISO 9606 & EN 13067

Via G. Corti 5, Balerna, Switzerland. Contact: [email protected]

SWISS APPROVAL INTERNATIONAL

Page 5: Inspection Test Plan (ITP) for Pipeline Construction ...

Third Party Inspection, Monitoring & Approval –ISO 17020 Accredited Standards & Scopes

Swiss Approval International is an ISO 17020 Accredited Inspection & Certification Body, authorized to conductInspections by highly experienced staff, as an independent Third-Party Organization, according to therequirements of National or International Standards.

Some of the most important sectors with Accreditation of Swiss Approval Inspection Services are according to:

❖ ASME V, VIII, IX, B31.3, B31.8, B31.1 etc.❖ API 650/653, 510, 570❖ EN 12732❖ Interpretation and Evaluation of Results using Test Methods as:

• Automatic Ultrasonic Testing with conventional probes (AUT)• Phased Array Ultrasonic Testing (PAUT)• Time of Flight Diffraction Ultrasonic Testing (TOFD)• Liquid Penetrant Testing (PT)• Magnetic Particles Testing (MT)• Ultrasonic Testing (UT)• Radiographic Testing (RT)• Visual Testing (VT)

Via G. Corti 5, Balerna, Switzerland. Contact: [email protected]

SWISS APPROVAL INTERNATIONAL

Page 6: Inspection Test Plan (ITP) for Pipeline Construction ...

A Large Variety of Industrial Inspection Services includes following Sectors:

- Refineries

- Tank Farms

- Pipelines [Offshore & Onshore]

- Power Plants

- Process Industries [Food, chemicals, etc.]

- Naval Industry [New Building & Maintenance]

- Transport Industry [Trains, Vessels, Planes]

Via G. Corti 5, Balerna, Switzerland. Contact: [email protected]

INDUSTRIAL INSPECTION SERVICES

Page 7: Inspection Test Plan (ITP) for Pipeline Construction ...

One by one, all the following methods describe in the best possible way why SwissApproval can and should be proud of its Innovation, in the Sector of Advanced NDTInspection.The following are mentioned:

• Guided Waves [GWT] – Long Range UT• Acoustic Emission• On-Line Safety Valves• On-Line Flanges Inspection • Heat Exchangers Inspection of Tubes• Phased Array & TOFD• Creeping Waves• Corrosion Mapping with Robotic Systems for Tanks & Vessels• AUT for Pipeline Construction• MFL for Bottom of Tanks & Pipe Scan• Wire Ropes Magnetic Inspection

ADVANCED NDT INSPECTION

Via G. Corti 5, Balerna, Switzerland. Contact: [email protected]

Page 8: Inspection Test Plan (ITP) for Pipeline Construction ...

Referring to Construction Projects, we should not forget that every project must have a planned sequence, of operations and especially in complex fabrications, planning and timely execution of all processes is crucial.

• Inspection & Test Plan, widely known as ITP is the Corner Stone of the Quality Control (QC) Process

• The purpose of an Inspection & Test Plan (ITP) is to provide a single document, that indicates all inspection and testing requirements, relevant to a specific process and provides records.

• The ITP is used by both, the Client and the Manufacturer and all-important items are signed off by both, as work progresses.

• An ITP should address the following:

➢ Inspection and test coverage,

➢ Inspection and test methods,

➢ Acceptance criteria, records, reports, and

➢ Inspection and test responsibilities

Inspection and Test Plan

Via G. Corti 5, Balerna, Switzerland. Contact: [email protected]

Page 9: Inspection Test Plan (ITP) for Pipeline Construction ...

• ITP is a very analytical Plan of when, what and how you will conductinspections to ensure your work is meeting all necessary Standards.

• It details the critical points at various stages, within a process forscheduled inspections and verifications, to make sure the job isprogressing as it should be.

• An ITP might refer to different checklists for each inspection point, or couldrefer to a code or standard, that sets out the requirements for what andhow the check must be performed,

• A simple ITP can closely match a checklist, but is not the same as anInspection Checklist.

• The Inspection & Test Plan is like a Work Instruction and the Checklist is aform that becomes the actual record. Both the ITP and Checklist aredocuments that must be controlled.

Inspection and Test Plan

Via G. Corti 5, Balerna, Switzerland. Contact: [email protected]

Page 10: Inspection Test Plan (ITP) for Pipeline Construction ...

The ITP’s function is to:

➢ Break down the Production Process into single tasks,

➢ Identify the items of materials and work to be inspected or tested,

➢ Identify parties responsible for the specific inspection or testing activities,

➢ Identify the stage of production and the frequency of inspection and testing

Identify important milestones & the Inspection Points:

➢ Hold (H),

➢ Witness (W),

➢ Spot Witness (SW),

➢ Monitoring (M),

➢ Review (R)

Inspection and Test Plan

Via G. Corti 5, Balerna, Switzerland. Contact: [email protected]

Page 11: Inspection Test Plan (ITP) for Pipeline Construction ...

Quality Management is the process of ensuring that all project activitiesnecessary to design, plan and implement a project are effective and efficientwith respect to the purpose of the objective and its performance. In simplewords, Quality Management is the attempt of assuring the successful deliveryof Quality products or services.

Project Management is the application of processes, methods, skills, knowledgeand experience to achieve specific project objectives according to the projectacceptance criteria. Project management has final deliverables that areconstrained to a very specific timescale and budget.

“Quality Management is everything we must do, to make sure we produceand deliver on time, but Project Management is about people getting thingsdone."

Quality Managementvs. Project Management

Via G. Corti 5, Balerna, Switzerland. Contact: [email protected]

Page 12: Inspection Test Plan (ITP) for Pipeline Construction ...

But from the point “what we must do”, to the point “the things we real do”,there is always a GAP, that changes the original calculations, and deviates fromthe original schedule.

To eliminate this gap Swiss Approval applies “Project Quality Management”Practice.

The main principle of Project Quality Management is to ensure, the project willmeet or even exceed its initial needs and expectations. Project qualitymanagement is the process, through which Quality, is managed and maintainedthroughout a project.

According to this concept, Swiss Approval always use its specialized personnel inorder to create a Team, responsible to run a Project by following and applying aspecific Inspection & Test Plan.

Quality Managementvs. Project Management

Via G. Corti 5, Balerna, Switzerland. Contact: [email protected]

Page 13: Inspection Test Plan (ITP) for Pipeline Construction ...

Swiss Approval’s running its Project Quality Management Conceptby the following specialized Team :

• Quality Manager

• NDT Level 3 Inspector

• Welding Engineers

• Welding Inspectors

• NDT Level 2 Inspectors

• Senior Project Manager (Primavera Certification)

• Project Managers (Primavera Certification)

• Data Controller Inspector

Project Quality Management

Via G. Corti 5, Balerna, Switzerland. Contact: [email protected]

Page 14: Inspection Test Plan (ITP) for Pipeline Construction ...

• Every Inspector has his own tablet which is connected online with Primavera Project Management Software.

• This solution helps to update the Inspection Test Plan in real time.

Outputs from Primavera

➢ Scheduling

➢ KPI Charts

➢ Schemes for the progress

➢ Control capabilities

Inspectors Equipment

➢ Welding Gauges Kit

➢ UT Thickness Gauge

➢ PMI (Identification for the Materials)

➢ Liquid Penetrant Testing Sprays for high temperatures testing up to 200°C

➢ Portable hardness tester

➢ Thermometer

Project Quality Management

Via G. Corti 5, Balerna, Switzerland. Contact: [email protected]

Page 15: Inspection Test Plan (ITP) for Pipeline Construction ...

Thank you

For your Attention

Via G. Corti 5, Balerna, Switzerland. Contact: [email protected]