IHRB Project TR-625 - 2014 Mid-Continent … 30 60 90 120 150 180 210 240 270 300 330 360 (µ ε)...
Transcript of IHRB Project TR-625 - 2014 Mid-Continent … 30 60 90 120 150 180 210 240 270 300 330 360 (µ ε)...
IHRB Project TR-625 Researchers:
Sri Sritharan Matt Rouse
Ebadollah Honarvar James Nervig Wenjun Hu
08/21/2014
2
Outline 3- Material Characterization
7-Long-term camber
predictions
6- Instantaneous
camber predictions
5- Long-term camber
measurements
4-Instantaneous
camber measurements
1- Problem Statement
2- Research Scope and Objectives
Problem Statement
3
Iowa Department of Transportation (Iowa DOT) currently uses the ConSpan program to predict the instantaneous camber with an assumption of elastic beam theory.
Long term camber is estimated using Martin’s multipliers (i.e.,1.80 for the deflection due to the effects of prestress and 1.85 for the self-weight deflection)
The current method frequently over-predicts the long-term camber of long beams in Iowa bridges, while underestimating the long-term camber of shorter PPCBs
Problem Statement
4
Overpredicting Camber: Ø Build haunches along the entire
length of the girder Ø Addditional nonprestressed
reinforcement (haunches exceeding four inches)
Underpredicting Camber: Ø Flexural cracking in the top flange
Ø Difficulty with field assembly
Ø Delays in construction schedule
Ø Serviceability problems with structures
Increase in the construction
costs
Research Scope and Objectives
5
Improve both short-term and long-term camber predictions, and minimize the error between the expected and actual camber of PPCBs especially at the time of erection.
Systematically, investigate the short-term and long-term material behavior, examine the camber measurement techniques, and quantify the camber from the time of construction of PPCBs until the completion of bridges.
The following objectives were used to achieve the project scope.
Research Scope and Objectives
6
1- Literature Review • Recent completed work on this research topic by other DOTs
2- Historical Camber Data
• Review existing recorded instantaneous and long-term camber data
3- Concrete Properties • Compressive strength, modulus of elasticity,
creep and shrinkage
4- Camber Measurements
• Various Iowa DOT PPCBs • At transfer, storage at the precast plants, erection, and
before/after the deck pour
5- Scatter in Measured Data • Potential sources of scatter in the measured data
• Camber measurement techniques, bed deflection support condition, and temperature effect
6- New Measurement Approach • Propose a new measurement technique
7- Instantaneous Camber Prediction • Improve the estimation of instantaneous camber
8- Long-term Camber Prediction
• Analytical models using Finite Element Analysis • Long-term multipliers
Material Characterizations
7
Ø 4 HPC, and 3 NC concrete mixes for compressive strength, creep and shrinkage
Ø Sealed and unsealed specimens
Compressive strength test of a cylindrical specimen
Sulfur-capped sealed and unsealed specimens
Material Characterizations
8
Ø Environmentally controlled chamber with the temperature of 73.4°F ± 2.0 °F (23.0°C ± 1.1
°C) and relative humidity of 50 ± 4 %
Ø A target stress of 2125 psi for creep test.
Loaded specimens for creep tests in the environmentally controlled chamber Details of a creep frame
Material Characterizations
9
Ø Demountable mechanical (DEMEC) strain gage was used to measure the change of length
between two vertical gage points attached to the concrete cylinders.
Device and Measurement of strain by using the DEMEC gage
Material Characterizations
10
Shrinkage Behavior of a 4-ft Beam Section
Ø Correlate the shrinkage behavior of actual beam and specimens in the laboratory.
Ø BTB beam section with a length of 4 feet was cast and stored in the yard of a precast plant.
Debonded 4-ft BTB Beam section stored in precast plant A
0
100
200
300
400
500
600
700
0 30 60 90 120 150 180 210 240 270 300 330 360
Shri
nkag
e (µε)
Age of Concrete, days
Sealed Shrinkage Unsealed Shrinkage 4-ft Beam Section Average Shrinkage Adjusted Unsealed Shrinkage ACI Top flange shrinkage Web shrinkage Bottom flange shrinkage
Comparison of shrinkage strains measured from a 4-ft. full-scale beam section and standard cylindrical
specimens
Material Characterizations
11
Average creep coefficient:
φ(t) = 1.9 t↑0.48 /8+ t↑0.54
Average shrinkage
strain: ɛ(t) = 480t↑0.60 /12+ t↑0.62
0
0.2
0.4
0.6
0.8
1
1.2
1.4
1.6
0 50 100 150 200 250 300 350 400
Cre
ep C
oeffi
cien
t
Time (days)
Average Measured AASHTO LRFD 2010 HPC1 HPC2 HPC3 HPC4
-550
-450
-350
-250
-150
-50
0 50 100 150 200 250 300 350 400
Mic
rost
rain
(µε)
Time (days)
Average Measured AASHTO LRFD 2010 HPC1 HPC2 HPC3 HPC4
Instantaneous Camber Measurements
12
Cur
rent
Indu
stry
Pra
ctic
e
Measure camber while beam is on the precasting bed
Within three hours of the transfer of prestress
At midspan with a tape measure Measured to the nearest 1/8 in.
Instantaneous Camber Measurements
13
Historical Camber
y = -5E-07x - 0.0023 R² = 0.0007
-0.0120
-0.0100
-0.0080
-0.0060
-0.0040
-0.0020
0.0000
0.0020
0.0040
0.0060
0.0080
(Mea
sure
d C
ambe
r - P
redi
cted
Cam
ber)
/Len
gth
Variety of Bulb-T Beams Arranged in Increasing Length
BTD-29D BTC50 BTC55 SBT17M SBT24M BTC80 BTC85 BTD85 BTC90 SBT99 BTC100 BTC105 BTC110 BTD110 BTC115 BT120 BTC120 BTD120 SBT38M BT125 BTD125 BT130 SBT130 BTD130 BT135 SBT135 BTD135 BTE135 BT140 SBTD148.58
Average = -.002411 Standard Deviation = .00258
Instantaneous Camber Measurements
14
Historical camber values on 1300 beams has given the
following trends:
Instantaneous camber for certain types of beams is overpredicted and
other times underpredicted.
Larger scatter is observed in shorter beams than in longer beams.
Values decrease with greater length.
Overpredicted 75% of the time.
Instantaneous Camber Measurements
15
Mea
sure
men
t Tec
hniq
ues
A tape measure reading is taken at the midspan of the beam after release (recorded to the nearest 1/16 in.)
A rotary laser level is used to measure the beam from the top flange and the bed (accurate up to 1/16 in. at 100 ft).
String Potentiometers have been installed on multiple points along the beam and precasting bed to determine the camber and how the precasting bed is reacting (accurate up to 0.015 in.).
Instantaneous Camber Measurements
16
New measurement technique is recommended to take into account
the aforementioned factors
Factors misrepresenting the recorded camber
Bed Deflections
Inconsistent Top Flange
Surfaces Friction
Instantaneous Camber Measurements
17
-0.025
-0.020
-0.015
-0.010
-0.005
0.000
0.005
0.010
0.015
0.020
0 1000 2000 3000 4000 5000
Vert
ical
Dis
plac
emen
t (in
.)
Time (sec)
Bed at Midspan Bed at Left End Events
Rel
ease
Beg
ins
Rel
ease
Com
plet
e
Lifte
d B
eam
-0.080
-0.060
-0.040
-0.020
0.000
0.020
0.040
0 1000 2000 3000 4000 5000 6000 7000 8000
Vert
ical
Dis
plac
emen
t (in
.)
Time (sec)
Bed at End of Beam Bed at Midspan Events
Rele
ase
Begi
ns
Rele
ase
Com
plet
e
Beam
shift
s 2.2
5"
Bed Deflection
Ø A Time vs. Displacement graph of the precasting beds shows that a downward deflection
can occur at the ends of the beam along with an upward deflection at the midspan.
Instantaneous Camber Measurements
18
Inconsistent Top Flange Surfaces
Ø Due to uneven surface conditions along the top flange, the location where camber
measurements are taken at the jobsite can cause a discrepancy of up to 0.90 in.
Instantaneous Camber Measurements
19
Friction
Ø Friction between the bed and beam inhibits camber at release. Lifting the beam after release
and then taking a measurement can cause an increase in the measured camber by an average
of 17%
0.00
0.50
1.00
1.50
2.00
2.50
3.00
3.50
4.00
4.50
5.00
Cam
ber
(in.)
Variety of Beams Arranged in Increasing Length
Effect of Friction on Camber Measurements
Before girder was lifted After girder was lifted
Instantaneous Camber Measurements
20
0.0
0.5
1.0
1.5
2.0
2.5
3.0
3.5
6000 6500 7000 7500 8000 8500 9000 9500 10000 10500
Vert
ical
Dis
plac
emen
t (in
.)
Time (seconds)
Top Flange at Midspan Events
Rel
ease
Com
plet
e
Lifte
d B
eam
Tota
l Inc
reas
e in
C
ambe
r due
to
Fric
tion.
Incr
ease
in C
ambe
r due
to
Bea
m E
nds
Ove
rcom
ing
Fric
tion.
In
crea
se in
Cam
ber d
ue
to
Lift/
Set o
f Bea
m.
Two components of Friction
Ø Increase due to beam ends sliding towards each other (Time 6300-8600 seconds)
Ø Increase in displacement when beam is lifted (Time 8600 seconds)
Instantaneous Camber Measurements
21
Rev
erse
Fri
ctio
n
“As the girder end is set on the bed, friction acts in the opposite direction to resist the weight of the girder pushing the girder end back outward.” (O’neill et al. 2012)
“The release cambers that might be obtained from a frictionless bed would be expected to lie somewhere between the initial on-bed release camber reading and the lift/set camber reading.” Ahlborn et al. (2000) used the average of the measured release camber and the lift/set camber as the assumed “true” release camber. Due to string potentiometer graphs, reverse friction, if any, is small in quantity.
Instantaneous Camber Measurements
22
PPCB with roller support under one end
Roller Support
Bea
m w
ith a
Rol
ler
Supp
ort
Beam 1-not lifted.
Beam 2-lifted and sat back down on the precasting bed.
Beam 3-a roller was placed under one end to simulate the effect of eliminating friction.
Instantaneous Camber Measurements
23 -0.1 0.0 0.1 0.1 0.2 0.2 0.3 0.3 0.4 0.4 0.5
4500 5000 5500 6000 6500 7000 7500
Vert
ical
Dis
plac
emen
t (in
.)
Time (sec)
Beam 1-No Lift or Roller Beam 2-Lifted Beam 3-Lifted with Roller
Rel
ease
Com
plet
e Lifting and setting the beam down eliminates
additional vertical displacement due to
friction
Rat
e of
Cam
ber
Gro
wth
Beam 1 has a larger rate of growth than Beam 2 and 3 (Friction is still present in Beam 1).
The beam with the frictionless roller (Beam 3) and beam that was lift/set (Beam 2) have the same rate of vertical growth.
Beam 3 is assumed to be frictionless (Increase in vertical displacement is due to creep and shrinkage).
Instantaneous Camber Measurements
24
Summary of Measurements Errors
Ø The following errors with camber measurement were observed
Measured Value Error
Ave. (inches) Std. Dev. (inches) Ave. Std. Dev. Maximum Minimum
Friction* 0.392 0.294 17.60% 8.83% 38.43% 1.41%
Inconsistent Top Flange Surface along
the Length of the Beam
0.099 0.142 5.15% 24.55% 29.14% 0.00%
Inconsistent Top Flange due to Local
Surface Effects 0.113 0.119 6.84% 7.58% 66.02% 0.00 %
Bed Deflections 0.030 0.062 2.79% 8.21% 16.13% 0.00%
Instantaneous Camber Measurements
25
1- Place a 2x4 on the top flange of the PPCB at the ends and at midspan.
2- Cast concrete to the elevation of the 2x4 to ensure that flat surface will be produced at the measurement points.
3- Allow beam to cure using standard practice.
4- Remove the 2x4’s from the top flange.
5- After the beam has been released, precasters’ have one of the following options: (a) Lift/set the beam on the precasting bed. (b) Lift the beam and move it to the storage yard, placing it on temporary wooden supports.
Proposed Measurement Technique:
Instantaneous Camber Measurements
26
.
.
6- Measure the elevation of the beam with a rotary laser level, total station, or other survey equipment at the midspan and ends at the locations where the 2x4s were placed. At each location, take measurements at the center and towards the edges of the top flange.
7- If option 5b is used, determine the contribution in camber due to the reduced clear span and overhang caused by the temporary supports.
8- Take the average of the end elevation readings and subtract from average midspan camber elevation reading.
9- If option 5b is used, subtract the contribution in camber due to the temporary support placement from the camber value calculated in step 8.
Long-term Camber Measurements
27
Beam Type C 80 D 55 D 60 D 105 BTC 120 BTD 135 BTE 110 BTE 145 Overall Length (m) 24.7 17.1 18.6 32.3 37.0 41.6 33.9 44.6 Jacking Force (KN ) 4163 2268 2651 6058 9461 10217 5676 9843 Number of Straight Tendons 16 12 14 26 38 42 26 42 Number of Harped Tendons 6 0 0 6 12 42 4 10 Theoretical Instantaneous Camber (mm) 41.7 6.1 8.9 61.5 87.6 90.7 40.9 75.4 Theoretical Long-term Camber (mm) 73.7 10.7 15.7 108.5 154.2 159.3 71.9 132.3 Number of Measured Beams 4 12 12 12 3 8 9 6 Number of Beam Sets 1 4 4 4 1 4 3 2 Age at Last Measurement 117 202 158 173 75 65 446 253
Dat
a C
olle
ctio
n
The beams fabricated for five different bridges in Iowa were monitored periodically for camber measurements during storage as well as at erection.
These selected beams included different types of Iowa DOT PPCBs with various lengths and depths.
The rotary laser lever was used to measure long-term camber from the top flange of the beams.
Long-term Camber Measurements
28
Varying overhang lengths with an average measured overhang length of L/30
Inconsistent trends in data primarily due to temperature effect
0.000
0.010
0.020
0.030
0.040
0.050
0.060
0 20 40 60 80 100
Ove
rhan
g le
ngth
/ G
irde
r L
engt
h
Overhang Length (in.)
D 55 D 60 C 80 D 105 BTE110 BTC 120 BTD 135 BTE145 a = L/ 30
2.0
3.0
4.0
5.0
6.0
7.0
8.0
4/1/2012 7/10/2012 10/18/2012 1/26/2013 5/6/2013
Mea
sure
d C
ambe
r (in
.)
Date
BTE 145-1 BTE 145-2 BTE 145-3 BTE 145-4
0.0
1.0
2.0
3.0
4.0
5.0
6.0
7.0
6/20/2012 7/10/2012 7/30/2012 8/19/2012 9/8/2012 9/28/2012
Mea
sure
d C
ambe
r (in
.)
Date
BTD 135-1 BTD 135-2 BTD 135-3 BTD 135-4 BTD 135-5 BTD 135-6 BTD 135-7 BTD 135-8
Observations:
Long-term Camber Measurements
29
Dat
a C
olle
ctio
n to
Inve
stig
ate
Tem
pera
ture
Eff
ect
Twenty-two different PPCBs were instrumented with string potentiometers and thermocouples to measure thermal camber as a function of temperature over a short duration.
Measurements were conducted for four different seasons. Two instrumented beams to determine vertical temperature gradient distribution over the cross section depth. Temperature was measured at every quarter point of depth for two beams (BTE 145, BTE 155) throughout the day
Long-term Camber Measurements
30
Instrumented PPCBs in Summer
Instrumented PPCBs in Winter
Long-term Camber Measurements
31
Thermocouples every quarter point over beam depth
S t r i n g potentiometer
BTE 145 BTE 155
Observed Behavior
32
0
10
20
30
40
50
60
70
-10 0 10 20 30 40 50
Dis
tanc
e fr
om b
otto
m o
f bea
m
(in.)
Temperature (°F)
4/9/2014 13:40 4/9/2014 15:00 4/9/2014 18:00 4/9/2014 21:00 4/10/2014 0:00 4/10/2014 3:00 4/10/2014 6:00 4/10/2014 9:00 4/10/2014 12:00 AASHTO LRFD 2010
0
10
20
30
40
50
60
70
-10 0 10 20 30 40 50
Dis
tanc
e fr
om b
otto
m o
f bea
m
(in.)
Temperature (°F)
4/9/2014 13:40 4/9/2014 15:00 4/9/2014 18:00 4/9/2014 21:00 4/10/2014 0:00 4/10/2014 3:00 4/10/2014 6:00 4/10/2014 9:00 4/10/2014 12:00 AASHTO LRFD 2010
Vertical Temperature Distribution:
BTE 155 Beam
BTE 145 Beam
Observed Behavior
33
-15
0
15
30
45
60
-0.3
0
0.3
0.6
0.9
1.2
6/5/2013 8:09 6/5/2013 13:55 6/5/2013 19:40 6/6/2013 1:26 6/6/2013 7:12
Tem
pera
ture
Gra
dien
t (°F
)
The
rmal
Cam
ber
(in.)
Time
BTE 145-1 BTE 145-2 BTE 145-3 BTE 145-4 BTE 145-5 BTE 145-6 Temperature Gradient
Wind speed: 10 mph Maximum wind speed: 22 mph Average humidity: 69%
-20
-10
0
10
20
30
40
50
60
-0.4
-0.2
0
0.2
0.4
0.6
0.8
1
1.2
1.4
7/18/2013 4:48 7/18/2013 12:57 7/18/2013 21:07 7/19/2013 5:16 7/19/2013 13:26
Tem
pera
ture
Gra
dien
t (°F
)
The
rmal
Cam
ber
(in.)
Time
BTC 115-1 BTC 115-2 BTC 115-3 BTD 115-1 BTD 115-2 BTD 115-3 Temperature Gradient
Wind speed: 8 mph Maximum wind speed: 18 mph Average humidity: 64 %
Thermal Camber and Temperature Gradient versus Time:
BTE 145 Beams in Summer (June)
BTC 115 Beams in Summer (July)
Observed Behavior
34
-15
0
15
30
45
60
-0.3
0
0.3
0.6
0.9
1.2
2/26/2014 7:12 2/26/2014 15:36 2/27/2014 0:00 2/27/2014 8:24 2/27/2014 16:48
Tem
pera
ture
Gra
dien
t (°F
)
The
rmal
Cam
ber
(in.)
Time
BTE 155-1 BTE 155-2 BTE 155-3 BTE 155-4 BTE 155-5 BTE 155-6 Temperature Gradient
Wind speed: 16 mph Maximum wind speed: 30 mph Average humidity: 73 %
-15
0
15
30
45
60
-0.3
0
0.3
0.6
0.9
1.2
4/9/2014 4:48 4/9/2014 14:24 4/10/2014 0:00 4/10/2014 9:36 4/10/2014 19:12
Tem
pera
ture
Gra
dien
t (°F
)
The
rmal
Cam
ber
(in.)
Time
BTE 155-1 BTE 155-2 Temperature Gradient
Wind speed: 10 mph Maximum wind speed: 28 mph Average humidity: 50%
BTE 155 Beams in Winter (February)
BTE 155 Beams in Spring (April)
Observed Behavior
35
-15
0
15
30
45
60
-0.3
0
0.3
0.6
0.9
1.2
4/9/2014 6:57 4/9/2014 15:21 4/9/2014 23:45 4/10/2014 8:09 4/10/2014 16:33
Tem
pera
ture
Gra
dien
t (°F
)
The
rmal
Cam
ber
(in.)
Time
BTE 145-1 BTE 145-2 Temperature Gradient
Wind speed: 10 mph Maximum wind speed: 28 mph Average humidity: 50%
BTE 145 Beams in Winter (February)
Instantaneous Camber Predictions
36
Use AASHTO LRFD 2010 Equation with
adjustment to estimated initial
compressive strength
Consider elastic shortening, seating
losses, and relaxation
Use AASHTO LRFD 2010
Equation
Use transformed
section
Factors Affecting Instantaneous Camber
Modulus of elasticity
Designed prestress
force Prestress
losses Sacrificial
prestressing strands
Transfer length
Section properties
Ø Multiply Target Strength by 1.4 to calculate Eci When specified Target f'ci ≤ 6000 psi Ø Multiply Target Strength by 1.1 to calculate Eci When specified Target f'ci > 6000 psi
Long-term Camber Predictions
37
0
1
2
3
4
5
6
7
8
9
0 1 2 3 4 5 6 7 8 9
Pred
icte
d C
ambe
r, in
.
Measured Camber, in.
Data Points 45 Degree +25% -25% 0
1
2
3
4
5
6
7
8
9
0 1 2 3 4 5 6 7 8 9
Pred
icte
d C
ambe
r, in
.
Measured Camber, in.
Data Points 45 Degree +25% -25%
Comparison of predicted camber and measured camber with overhang by using
Naaman’s Method
Comparison of predicted camber and measured camber without overhang by using Naaman’s
Method
Sim
plifi
ed
Ana
lysi
s Tadros’s Method
Naaman’s Method ( The most accurate method)
Incremental Method
Long-term Camber Predictions
38
Fini
te E
lem
ent A
naly
sis
(FE
A)
Various parameters that could potentially affect camber such as creep and shrinkage, changes in prestress, support condition, and temperature effect were incorporated into the finite element models.
Study the change in camber of PPCBs from release to the time of erection with and without girder overhang.
Long-term Camber Predictions
39
Finite Element Analysis (FEA) Ø Beams were classified based on their estimated instantaneous camber into two groups as
follows :
0
0.5
1
1.5
2
2.5
3
3.5
4
0 20 40 60 80 100 120 140 160 180
Rel
ease
Cam
ber (
in.)
Overall Length (ft)
A B C D BTC BTD BTB BTE
Large Camber Beams
Small Camber Beams
Small camber beams: Instantaneous camber ≤ 1.5 in. Large camber beams: Instantaneous camber > 1.5 in.
Long-term Camber Predictions
40
0.0
0.4
0.8
1.2
1.6
2.0
2.3
2.7
3.1
0
10
20
30
40
50
60
70
80
0 100 200 300 400 500 600
Cam
ber (
in.)
Cam
ber (
mm
)
Time (days)
Camber-Without Overhang Camber-With Overhang
0.0
0.4
0.8
1.2
1.6
2.0
2.4
2.8
3.1
3.5
0
10
20
30
40
50
60
70
80
90
0 100 200 300 400 500
Cam
ber (
in.)
Cam
ber (
mm
)
Time (days)
Adjusted Measured Camber Original Measured Camber
Support Conditions Ø Eliminate the contribution of overhangs to camber (elastic and creep components).
Analytical camber curves for a BTE 110 Measured and adjusted data for a BTE 110
Long-term Camber Predictions
41
Thermal Camber
Ø linear vertical temperature distribution over the cross section would create the maximum
thermal camber compared to the polynomial temperature distribution
y = 0.0319x - 1E-16 R² = 1
-0.1 0.0 0.1 0.2 0.2 0.3 0.4 0.5 0.5 0.6 0.7 0.8
0 2 4 6 8
10 12 14 16 18 20
0 5 10 15 20 25
Ther
mal
Cam
ber (
in.)
Ther
mal
Cam
ber (
mm
)
Temperature Gradient,ΔT (°C)
BTE 0.00
0.20
0.40
0.60
0.80
1.00
1.20
1.40
0 5 10 15 20 25 30 35 40 45
Mea
sure
d / D
esig
n C
ambe
r
Temperature Gradient, ΔT (°F)
Average
The average temperature gradient with the minimum error is 15 °F (8.3 °C)
Long-term Camber Predictions
42
M = 1.145 t0.043 R² = 0.983
0.00
0.20
0.40
0.60
0.80
1.00
1.20
1.40
1.60
1.80
2.00
0 100 200 300 400 500 600
Mul
tiplie
r, M
Age (Day), t
Average BTE 110 Average BTC 120 Average BTD 135 Average BTE 145 Average D 105 Average C 80 Average of All Large Camber Beams Power (Average of All Large Camber Beams)
Ø A set of multipliers without overhang (0-60 days; 60-180 days; and over 180 days) Ø Temperature gradient multiplier, λT ( Use ΔT= 15°F) Ø A set of multipliers with an average overhang length of L/30 (0-60 days; 60-180
days; and over 180 days) Ø A Single multiplier (Average at-erection age: 120 days)
Multipliers as a function of time:
Ø Multipliers were produced by comparing the instantaneous camber to long-term camber
predictions:
Long-term Camber Predictions
43
A representative of Results
0.00
0.25
0.50
0.75
1.00
0 50 100 150 200 250 300
Cam
ber (
in.)
Time (day)
Analytical Curve with ΔT= 0 °F Analytical Curve with ΔT= 15 °F Iowa DOT Long-term Camber Camber with Multipliers Camber with Multipliers ,ΔT= 15 °F Set 2 Average Data
0.00
0.50
1.00
1.50
2.00
2.50
3.00
3.50
4.00
4.50
0 50 100 150 200 250 300
Cam
ber (
in.)
Time (day)
Analytical Curve with ΔT= 0 °F Analytical Curve with ΔT= 15 °F Iowa DOT Long-term Camber Camber with Multipliers Camber with Multipliers ,ΔT= 15 °F Set 2 Average Data
D 105 Beams
0.00
0.50
1.00
1.50
2.00
2.50
3.00
3.50
4.00
0 50 100 150 200 250 300 350 400 450 500
Cam
ber (
in.)
Time (day)
Analytical Curve with ΔT= 0 °F Analytical Curve with ΔT= 15 °F Iowa DOT Long-term Camber Camber with Multipliers Camber with Multipliers ,ΔT= 15 °F Set 1 Average Data
BTE 110 Beams
0.00
1.00
2.00
3.00
4.00
5.00
6.00
7.00
0 50 100 150 200 250 300
Cam
ber (
in.)
Time (day)
Analytical Curve with ΔT= 0 °F Analytical Curve with ΔT= 15 °F Iowa DOT Long-term Camber Camber with Multipliers Camber with Multipliers ,ΔT= 15 °F Set 1 Average Data
BTE 145 Beams
D 55 Beams
Comparison of Different Long-term Camber Prediction Methods
44
Ø Method 1, (M1): Multiplier Function with adjusted data for overhang Ø Method 2, (M2): Set of multipliers- no overhang Ø Method 3, (M3): Set of multipliers- with overhang Ø Method 4, (M4): Single Multiplier-without overhang Ø Method 5, (M5): Single Multiplier-with overhang Ø Method 6, (M6): Current Iowa DOT approach
Long-term Camber Prediction Methods: 0.
22
-0.0
4
0.18
-0.0
8
0.19
-0.1
1 0.12
0.13
-0.1
7
0.44
0.46
0.54
0.60
0.72
0.78
0.58
0.77
0.71
-0.40
-0.20
0.00
0.20
0.40
0.60
0.80
1.00
M1, ΔT= 0°F
M1, ΔT= 15°F
M2, ΔT= 0°F
M2, ΔT= 15°F
M3, ΔT= 0°F
M3, ΔT= 15°F
M4 M5 M6
(Mea
sure
d C
ambe
r-Des
ign
Cam
ber)
(in.
)
Prediction Method
Average and Standard Deviation of Each Method
Average Standard Deviation
93
93
89
85
80
80
89
75 79
0 10 20 30 40 50 60 70 80 90
100
M1, ΔT= 0°F
M1, ΔT= 15°F
M2, ΔT= 0°F
M2, ΔT= 15°F
M3, ΔT= 0°F
M3, ΔT= 15°F
M4 M5 M6
-1''<
(Mea
sure
d C
ambe
r-Des
ign
Cam
ber)
(%)
< 1'
'
Prediction Method
Percentage of Data within ±1.0 in.
Assumption: No construction difficulties in the field if the difference between the measured and design camber is within ±1.0 in..
Conclusions
45
Modify the current instantaneous camber measurement techniques based on the new recommendations.
Store the beams without overhangs at the precaster’s yard.
Use the proposed equations to predict time-dependent behavior of HPC.
Assume an average temperature gradient of 15 °F (8.3 °C) for camber measurements/analysis.
FEA predicted long-term camber most accurately; however, a single multiplier with overhang adjustment can still significantly improve camber predictions compared to the current Iowa DOT approach.
Use different multipliers for small camber beams and large camber beams.