Download - Status of LHC installation & New Installation Schedule

Transcript
Page 1: Status of LHC installation & New Installation Schedule

19 June 2007 Sylvain Weisz - LEMIC 1

Status of LHC installation&

New Installation Schedule

Page 2: Status of LHC installation & New Installation Schedule

LSS1R Q1 & Q3 reparation on surface, transport and lowering of low-β scheduled CW27-29

Arc 1-2 & DS Interconnection in progress, global advancement ~35%

TI2 Magnets (MQI/MBI) and TED in place, beam-pipe installation in progress

last LHC Arc cryo-magnets in UJ22 (MB2311/SSS652/MB3390) in place

LSS2L Short circuit tests in progress MKI not available, Alice ZDC installation CW24-25 Low-β repair & interconnection takes up to CW43 critical for completion of Sector 1-2

LSS2R Q3.R2 on surface, DFBAD HCM in place, LCM available July 4th

Short circuit tests completed last week Arc 2-3 & DS

Interconnection in progress: ~70% global advancement Q11.R2 has a short and will be replaced (SSS ready CW32) impact on interconnect activity

LSS3L/R DSLC: leaky compensators on thermal shield lines, should be replaced Q6.L3 and DFBMD available, installation pending completion of DSLC Installation of last warm magnets postponed, pending DSLC installation Modification of power cabling in UJ33 scheduled CW23-2719 June 2007 Sylvain Weisz - LEMIC 2

Sector 1-2, 2-3 & Point 3

Planning issue

Page 3: Status of LHC installation & New Installation Schedule

Low-β repair: conceptual drawing to implementation

Cartridge model for fixed point reinforcement

Cartridge installation in Q1.R1 (done in Bld. 181)

Page 4: Status of LHC installation & New Installation Schedule

LSS1R Q1 & Q3 reparation on surface, transport and lowering of low-β scheduled CW27-29

Arc 1-2 & DS Interconnection in progress, global advancement ~35%

TI2 Magnets (MQI/MBI) and TED in place, beam-pipe installation in progress

last LHC Arc cryo-magnets in UJ22 (MB2311/SSS652/MB3390) in place

LSS2L Short circuit tests in progress MKI not available, Alice ZDC installation CW24-25 ??? Low-β repair & interconnection takes up to CW43 critical for completion of Sector 1-2

LSS2R Q3.R2 on surface, DFBAD HCM in place, LCM available July 4th

Short circuit tests completed last week Arc 2-3 & DS

Interconnection in progress: ~70% global advancement Q11.R2 has a short and will be replaced (SSS ready CW32) impact on interconnect activity

LSS3L/R DSLC: leaky compensators on thermal shield lines, should be replaced Q6.L3 and DFBMD available, installation pending completion of DSLC Installation of last warm magnets postponed, pending DSLC installation Modification of power cabling in UJ33 scheduled CW23-2719 June 2007 Sylvain Weisz - LEMIC 4

Sector 1-2, 2-3 & Point 3

Planning issue

Page 5: Status of LHC installation & New Installation Schedule

19 June 2007 Sylvain Weisz - LEMIC 5

Sector 3-4 & 4-5

Arc 3-4 & DS Interconnection in progress, global advancement ~95% 10 vacuum sub-sectors (out of 14) delivered to VAC, 7 leak tight and 3 under test Reparation on-going on 500 series SSS (Q7-Q11.R3), need to open cold masses

hold completion of interconnect in arc 3-4

LSS4L/R All elements in place, NEG activation of straight section completed this week

BGI detector damaged using wrong bake-out cycle! Klystron power tests in progress in UX45 Short to ground on MCB circuit in Q5.R4 reparation after 1st HW commissioning period of sector 4-5

Arc 4-5 & DS Interconnection completed, pressure test passed successfully on May 11-12th

He flushing in progress Cryo instrumentation checks, ELQA at warm and polarity checks in progress Replacement of 28 Velan valve puppets end of this week

Cool-down of Sector 4-5 starts CW26 (next week) LSS5L

Low-β: DFBX/Q3/Q2/Q1.L5 back on surface for repair Cool-down 4-5 without low-β Power test of warm magnets (D1.L5) completed First Roman Pots station in place

Page 6: Status of LHC installation & New Installation Schedule

19 June 2007 Sylvain Weisz - LEMICC 6

LSS5R Reparation of low-β fixed points scheduled CW27-33 critical path for completion of Sector 5-6 Power test of D1.R5 completed, test of low-β wire based alignment system in progress Interconnect Q4/Q5/Q6-DSLE and Q7-DFBAJ in progress

Arc 5-6 and DS Interconnection in progress, global advancement ~90%, 5 vacuum sub-sector completed

LSS6L DFBAK: HCM, LCM and LEJL connection cryostat in place Special configuration of DFBAK Proximity Equipment requiring extra ELQA (TP2) in place MKD tests in progress, difficult co-activity with dump line installation

dump line completion resumes after August 15th

LSS6R Installation of MKD and MKB tests in progress DFBAL HCM and LCM in place, ELQA (TP2) on-going with proximity equipment in place

Arc 6-7 & DS: Interconnect in progress, global advancement ~55%

LSS7L/R Preparation for warm magnet tests in progress (alignment smoothing done) - tests scheduled CW25-28 Collimator supports in place, collimator installation starts CW29 after warm magnet tests

Sector 5-6, 6-7 & Point 7

Page 7: Status of LHC installation & New Installation Schedule

Cryogenics conditions are now very stable below λ point Ice accumulation problems on current leads have been solved with the installation of dry air bags D2, Q4 & Q5 (4.5K magnets) have been powered to their nominal current (6 kA) Main arc circuits (MB & QF/QD) and correctors chains have been qualified at cold Quench protection systems and associated heaters have been validated Tests of Powering Interlock Controller are almost complete

Powering of the arc magnets is imminent … But repairs in sector 7-8 (replacement of 1055, PIMs, bus-bar on SSS 500, etc…) start early August

Need 4 weeks for warm-up, power tests have to stop prematurely

19 June 2007 Sylvain Weisz - LEMIC 7

Temperature stabilisation and Power tests

Sector 7-8

Page 8: Status of LHC installation & New Installation Schedule

19 June 2007 Sylvain Weisz - LEMIC 8

Sector 8-1

LSS8R Low-β: HX reparation completed, interconnect (H pieces) completed,

fixed point strenghtening (cartridge installation) CW25-31 critical path for completion of Sector 8-1

Test of LHCb warm compensators (MBXW) completed Y vacuum chamber available: D1-D2 vacuum installation in progress

Arc 8-1 Interconnections completed

Pressure test passed with success on June 9-10th

LSS1L Interconnection of DFBLA to DSLA completed Installation of D1-D2 vacuum chamber in progress Low-β: HX reparation completed, interconnect (H pieces) completed,

fixed point strenghtening (cartridge installation) CW25-31 critical path for completion of Sector 8-1

Page 9: Status of LHC installation & New Installation Schedule

Interconnections: Completed in Sectors 7-8, 8-1 & 4-5, pressure tests Ok 92% of magnet to magnet electrical connections done, 51% of W closures completed

Expect closure of sector 1-2 (arc & DS), incl. leak tests, by end of September Uncertainties and delays from repair of Serie 500 bus-bar insulation

Preparation for short circuit tests: Tests in progress in Point 2L (14/15 power station tested) Preparation for tests in Point 1R on schedule Tests in UJ33 will be re-done after modification of power cables routing

Installation of warm beam pipes in long straight sections: Components procurement Ok, ~200m/wk installed and activated Advancement below expected rate, perturbed by:

Area not available: LSS3L/R or UJ62-63 (for dump line) Co-activities: Point 6 (with kicker), Point 8R (with warm magnet tests) Uncertainty on equipment installation: collimators in LSS7L/R

19 June 2007 Sylvain Weisz - LEMIC 9

Installation Summary

Page 10: Status of LHC installation & New Installation Schedule

25 May 2007 Sylvain Weisz - ICC 10

Installation rate of LSS warm beam pipe

Courtesy of Miguel Jimenez

Page 11: Status of LHC installation & New Installation Schedule

Beam Commissioning to 7 TeV

.

.

Operation testing of available sectors

LHC Construction and InstallationGeneral co-ordination Schedule

12 23 34 45 56 67 78 81

Machine Checkout

Consolidatio

n

LHC project Document N°

LHC-PM-MS-0005.1 rev. 4.0

CERN Dep./Group/Contractor Document N°.

TS/IC

EDMS Document N°.

102509

Interconnection of the continuous cryostat

Leak tests of the last sub-sectors

Inner Triplets repairs & interconnections

Global pressure test &Consolidation

Flushing

Cool-down

Warm up

Powering Tests

12 June 2007

Prepared by Katy Foraz

Page 12: Status of LHC installation & New Installation Schedule

19 June 2007 Sylvain Weisz - LEMIC 12

New Installation Schedule - General Features

Sector 4-5: Arc & DS ready cool-down without low- Sector 3-4: Delays with DSLC cool-down without DSLC

Get experience with HW commissioning of 2 sectors in parallel Time window for fixes after 1st HW commissioning period

Need for an extra warm-up/cool-down cycle

Sector 7-8: Repairs scheduled Aug.-Sept. power tests stop early July Sector 8-1: Repair low- (8R & 1L) before cool-down

Need to warm-up sector 7-8 before completion of first power tests programCool-down and test low- as early as possible

HW commissioning directly up to 7 TeVNeed to commission many sectors in parallelGet ready for physics by summer 2008