GMn experiment engineering & design status

Robin Wines

October 20181

Page 2: Click to add title€¦ · Title: Click to add title Author: dchopard Created Date: 10/29/2018 10:17:47 AM ...

Components of GMn & Calibration

October 20182

GMn experiment requires• SBS• BB and detectors• HCal & CDet

Calibration setup requires• HRS-left• SBS• HCal & CDet

09019 Hydrogen/Deuterium Experimental Points 10cm Hydrogen/Deuterium

Q2 [GeV2]

θBB [deg]

dBB [m]

θ48D48 [deg]

d48D48 [m]

dHCAL [m]

Beam Line Configuration #

3.5 32.5 1.80 31.1 2.0 7.2 3 4.5 41.9 1.55 24.7 2.25 8.5 3 5.7 58.4 1.55 17.5 2.25 11 3 8.1 43 1.55 17.5 2.25 11 3 10.2 34 1.75 17.5 2.25 11 3 12.0 44.2 1.55 13.3 2.25 14 3

13.5 33.0 1.55 14.9 3.1 17 4

Calibration Points: 10cm Hydrogen

Q2 [GeV2]

θHRS [deg]

θ48D48 [deg]

d48D48 [m]

dHCAL [m]

Beam Line Configuration #

4.4 39 25.5 3.1 17. 4 4.4 42 25.5 3.1 17. 4 6.0 61.1 14.9 3.1 17. 4 6.0 64.3 14.9 3.1 17. 4 6.0 67.5 14.9 3.1 17. 4 6.0 70.7 14.9 3.1 17. 4

Page 3: Click to add title€¦ · Title: Click to add title Author: dchopard Created Date: 10/29/2018 10:17:47 AM ...

GMn Layout

October 20183

SBS and HCal

BB

Page 4: Click to add title€¦ · Title: Click to add title Author: dchopard Created Date: 10/29/2018 10:17:47 AM ...

Calibration Layout

October 20184

HRS-L

SBS

HCal

Page 5: Click to add title€¦ · Title: Click to add title Author: dchopard Created Date: 10/29/2018 10:17:47 AM ...

SBS Equipment

October 20185

Scattering Chamber-existing

Front Field Clamp-done

Corrector Magnets-done

48D48 Magnet-done

Counterweight Support Structure-done

Exit Beam Pipe-in assembly

Hcal & CDet- in assembly

Page 6: Click to add title€¦ · Title: Click to add title Author: dchopard Created Date: 10/29/2018 10:17:47 AM ...

Status

October 20186

ITEM STATUSHall A & UtilitiesFloor rise at the pivot needs survey & concrete leveling during install

Floor plates

GMn uses 10 of 15 SBS floor plates, Have 10 plates. GMn uses 9 of 16 HCAL floor plates, Catania has 7 plates on order.

Move BB rails to BL during installHRS-BR interferences - move air handler, move catwalk post at pivot, install access platform to access cryo can at pivot Modify & use Tritium platform, pre-install workLCW upgrade needs engineering check & purchase

BEAMLINEClear utilities supported along existing beamline during installMove and modify existing beamline supports during installModify existing beamline flanges doneNew beamline conical pipe doneBeamline shielding doneBeamline assembly hardware design tested, needs purchasingSupport tower doneSupport tower extension delivery Nov 30, 2018Vertical supports redesigned, needs purchasingCorrector magnets done

Page 7: Click to add title€¦ · Title: Click to add title Author: dchopard Created Date: 10/29/2018 10:17:47 AM ...

Status

October 20187

ITEM STATUSSBS MAGNET

Magnet modificationsassembled and tested, need holes for field clamp mounts

Counterweight support structureassembly tested, blocks need painting and holes for mount attachments

Magnet sub-assembly stand needs engineering and purchaseField clamps done

HCALDetector frame assembly parts and frame doneSupport redesigned, need drawings and purchasingPersonnel Access platform need drawings revised and purchasing

CDETFrame doneAssembly and mounting parts need design and engineering checks and purchasing

BigBiteFrame modifications done, in assemblyMagnet interferences check at installDetector stack base support needs design & engineering check

Page 8: Click to add title€¦ · Title: Click to add title Author: dchopard Created Date: 10/29/2018 10:17:47 AM ...

Status

October 20188

ITEM STATUSElectronics ShieldingMain hut doneBB GEM hut done(new GEM hut for side of SBS support) needs design

Target chamber need to purchase windows

Sieve plate and holder needs purchasing

Page 9: Click to add title€¦ · Title: Click to add title Author: dchopard Created Date: 10/29/2018 10:17:47 AM ...

Summary

October 20189

Completion requires 24 mw design and 18 mw engineering

Hall A has staff of 2 engineers, 1 associate engineer and 3 designers.

Present workload and priorities, allow all SBS GMn engineering & design to be complete by mid-March 2019. This does not include fabrication. The GEn polarimeter design work is not included in this schedule.