Renewable energy course#03

67

Transcript of Renewable energy course#03

Page 1: Renewable energy course#03
Page 2: Renewable energy course#03
Page 3: Renewable energy course#03
Page 4: Renewable energy course#03
Page 5: Renewable energy course#03
Page 6: Renewable energy course#03
Page 7: Renewable energy course#03
Page 8: Renewable energy course#03
Page 9: Renewable energy course#03
Page 10: Renewable energy course#03
Page 11: Renewable energy course#03
Page 12: Renewable energy course#03
Page 13: Renewable energy course#03
Page 14: Renewable energy course#03
Page 15: Renewable energy course#03
Page 16: Renewable energy course#03

20kVar

Page 17: Renewable energy course#03
Page 18: Renewable energy course#03
Page 19: Renewable energy course#03
Page 20: Renewable energy course#03
Page 21: Renewable energy course#03
Page 22: Renewable energy course#03
Page 23: Renewable energy course#03
Page 24: Renewable energy course#03
Page 25: Renewable energy course#03
Page 26: Renewable energy course#03
Page 27: Renewable energy course#03
Page 28: Renewable energy course#03
Page 29: Renewable energy course#03

Solar Power

Page 30: Renewable energy course#03
Page 31: Renewable energy course#03
Page 32: Renewable energy course#03

Designing & Fabrication of a 2-kW Parabolic Trough Solar Thermal Power Plant

Page 33: Renewable energy course#03
Page 34: Renewable energy course#03
Page 35: Renewable energy course#03

10

Concrete

Pillar

Solar

Cooker

Booster

Mirror

Nylon

Chord

Tracker

Base

Curved

Steel Pipe

Water

Container

Intravenous

Drip Set

Page 36: Renewable energy course#03
Page 37: Renewable energy course#03

α β

I

I' = I / Sin α

I'' = I' Sin (α+ β)

Solar Cooker Box

Booster MirrorI''' = I'' Sin (α+2β–180o)/Sin(180o–α–β)

LB

L

α+2β–180o

180o–α–β

Page 38: Renewable energy course#03
Page 39: Renewable energy course#03
Page 40: Renewable energy course#03
Page 41: Renewable energy course#03

Tracking Circuit

Two 6-Volt Batteries

Lead wires

Electric Motor

Motion synchronizing strip

Circular end attachments of primary mirror strips mounted on wooden frame

Threaded end rod

Page 42: Renewable energy course#03
Page 43: Renewable energy course#03
Page 44: Renewable energy course#03

α β

I

I' = I / Sin α

I'' = I' Sin (α+ β) 180o–α–β

Horizontal Surface

Freznel CollectorSolar Altitude

Page 45: Renewable energy course#03

Performance AnalysisSolar Irradiance at Noon in Karachi – 22 Years Avg.

Month

Jan. Feb Mar April May June July Aug. Sept. Oct. Nov. Dec.

Inoon 0.52 0.59 0.67 0.77 0.79 0.76 0.69 0.67 0.66 0.64 0.56 0.50

I = Inoon Sin [ 180 (t – tsunrise) / (tsunset – tsunrise) ] (W/m2)

Iact(t) = I Sin (α+θ) / Sin(α) (W/m2)

α = Sin-1[Sin δ Sin φ + Cos δ Cos ω Cos φ] (degrees)

ω = 15 (ts – 12) (degrees)

δ = Sin-1 [0.39795 Cos [0.98563 (N-173)]] (degrees)

Φ = Latitude

Page 46: Renewable energy course#03

Performance Analysis t2

Eexp = A € ∫ Iact(t) dt (Joules)

t1

Etheo = M C (T2 – T1)

€ = Eexp / Etheo

€ = 1837 kJ / 4515 kJ = 0.407

Page 47: Renewable energy course#03
Page 48: Renewable energy course#03
Page 49: Renewable energy course#03
Page 50: Renewable energy course#03
Page 51: Renewable energy course#03
Page 52: Renewable energy course#03
Page 53: Renewable energy course#03

Pakistan’s Solar Map

Page 54: Renewable energy course#03
Page 55: Renewable energy course#03

Monthly Averaged Global Solar Radiation on Five Major Cities of Pakistan

0

5

10

15

20

25

30

35

1 2 3 4 5 6 7 8 9 10 11 12

Month of the Year

Rad

iati

on

En

erg

y (

MJ/m2 /d

ay)

Page 56: Renewable energy course#03
Page 57: Renewable energy course#03
Page 58: Renewable energy course#03

Solar Resource

Pakistan (Around Quetta) 28-30oN 2200 0.81 0.75

Estimate ~ 85 x 1012 kWh/y ~ 25 times the total installed capacity

(~ 40,000 km2) of Pakistan at 5% conversion efficiency

Page 59: Renewable energy course#03

Solar Electric Generating Systems (SEGS - 1985)

Cost / kWh: 25¢ in 1985 – 10-13¢ today

Page 60: Renewable energy course#03

5 fields of 33 MW each Operational and commercially viable since 1985 15 additional years working life expected

Mojave Desert at Kramer Junction, California

Page 61: Renewable energy course#03
Page 62: Renewable energy course#03
Page 63: Renewable energy course#03
Page 64: Renewable energy course#03
Page 65: Renewable energy course#03

750 MW Imperial Valley Project of 250 kW Solar Dish Striling Engines

Page 66: Renewable energy course#03

Linear Freznel

Page 67: Renewable energy course#03

Concentrating Solar Thermal Power

• CSP capacity expected to double every 16 months over the next five years

• Worldwide installed CSP capacity will reach 6,400 megawatts in 2012

• CSP Costs expected: 7–10¢ per kilowatt-hour by 2015 and to 5–7¢ per kilowatt-hour by 2020

• CSP and PV plants may produce 69 percent of U.S. electricity and 35 percent of total U.S. energy, including transportation, by 2050