LASA Medium-β Cavity Progress Update Paolo Michelato 2 nd ESS Collaboration Meeting - SRF...

13
LASA Medium-β Cavity Progress Update Paolo Michelato 2 nd ESS Collaboration Meeting - SRF Elliptical Cavities 15 th December 2015

description

Nb LG and FG for prototypes Nb LG (diam. 480 mm), from CBMM arrived in Europe, sliced at Heraeus Hanau. RRR: about 300 Next steps BCP (a few  m) and heat treatment for dehydrogenation and stress release at EZ Dies preparation Deep drawing test Order for FG material for LG cavity prototype (tubes, stiffening) and for FG cavity prototype (sheets, tubes, stiffening) for the second medium beta is under way.

Transcript of LASA Medium-β Cavity Progress Update Paolo Michelato 2 nd ESS Collaboration Meeting - SRF...

Page 1: LASA Medium-β Cavity Progress Update Paolo Michelato 2 nd ESS Collaboration Meeting - SRF Elliptical Cavities 15 th December 2015.

LASA Medium-β Cavity Progress Update

Paolo Michelato

2nd ESS Collaboration Meeting - SRF Elliptical Cavities15th December 2015

Page 2: LASA Medium-β Cavity Progress Update Paolo Michelato 2 nd ESS Collaboration Meeting - SRF Elliptical Cavities 15 th December 2015.

Summary• Nb material: LG and FG, defects.• Interfaces, mechanical constrains, tolerances, boundaries

condition, etc for cavities and tank• Frames for cavity handling• QA / QC and Quality control strategy

Page 3: LASA Medium-β Cavity Progress Update Paolo Michelato 2 nd ESS Collaboration Meeting - SRF Elliptical Cavities 15 th December 2015.

Nb LG and FG for prototypes• Nb LG (diam. 480 mm), from CBMM

arrived in Europe, sliced at Heraeus Hanau.

• RRR: about 300

Next steps• BCP (a few mm) and heat treatment

for dehydrogenation and stress release at EZ

• Dies preparation• Deep drawing test

• Order for FG material for LG cavity prototype (tubes, stiffening) and for FG cavity prototype (sheets, tubes, stiffening) for the second medium beta is under way.

Page 4: LASA Medium-β Cavity Progress Update Paolo Michelato 2 nd ESS Collaboration Meeting - SRF Elliptical Cavities 15 th December 2015.

Nb defectsStill open the question of defects?

• XFEL statistics: between 0.6% and 2% (company dependent) for a XFEL sheet (265 x 265 mm2).

• “Propagation” of defects probability for ESS? Linear? • Sheets would be around 500 x 500 mm2. • Surface ratio: about 3.2• Expected defects ratio for ESS?• Scanning needed? All defects seen with eddy current are dangerous?

• The BCP treatment reduce the risk: it would corrode and remove “easily” defects with respect to EP

• Acceptable?

Page 5: LASA Medium-β Cavity Progress Update Paolo Michelato 2 nd ESS Collaboration Meeting - SRF Elliptical Cavities 15 th December 2015.

Mechanical construction, interfaces and plug compatibility

LASA plug compatible design needs for a full clarification of interfaces requirements.

Interfaces must be clarified: definitions, dimensions, tolerances, maximum misalignments, etc. to ensure the cavities acceptance and their installation in the cryomodule.

Present CEA cavity design should be updated and improved to be ready for series production. E.G. for cavity length (XFEL +/- 3 mm), definition of reference surfaces, flange tolerances, alignments, etc .

These activities already started after the Interface Meeting at LASA of November 2 – 3 and it is in progress.

Page 6: LASA Medium-β Cavity Progress Update Paolo Michelato 2 nd ESS Collaboration Meeting - SRF Elliptical Cavities 15 th December 2015.

Tank design• Present CEA tank design doesn’t permit the adjustment of the

tank length with respect to the cavity length. • Tank is “custom-made” and adapted to the cavity.• Present tank design makes quite hard the extraction of the

cavity from the tank: from EXFEL experience some cavities could need a further etching and therefore a cavity retuning for field flatness restoring.

The suggestion, coming from the past experience, is to insert an L structure sliding join on the tank: this will permit the adjustment of the tank length (one tank design for all cavities) and an easier removal of the tank and the installation of a new one after retreatment.

Page 7: LASA Medium-β Cavity Progress Update Paolo Michelato 2 nd ESS Collaboration Meeting - SRF Elliptical Cavities 15 th December 2015.

Tank designImplication of the presence of the join on the cavity installation in the module are under investigation by CEA (fixed point, tie rods distances and connections to the cryomodule frame, position of the sliding part w.r.t. coupler, etc)

Page 8: LASA Medium-β Cavity Progress Update Paolo Michelato 2 nd ESS Collaboration Meeting - SRF Elliptical Cavities 15 th December 2015.

Frames for cavity movement, support, cold test• CEA frames will be used

for medium beta cavity support, handling, movement, cold test, transportation.

• Same interaxis distance of rods for naked cavity and cavity with tank

• Rods: Titanium• Verification of

compatibility at the industry (cleaning, rinsing, BCP, HPR) under way.

Page 9: LASA Medium-β Cavity Progress Update Paolo Michelato 2 nd ESS Collaboration Meeting - SRF Elliptical Cavities 15 th December 2015.

Quality Control strategyBased on our experience for XFEL cavity production• 400 + 400 cavities (1.3GHz) fully produced at the industry +

10 + 10 cavities (3.9 GHz) produced at the industry (assembly of cavities ancillaries and last HPRs done at LASA), test done at LASA

For the 32 medium beta cavities for ESS:• Companies are responsible for QA/QC• Companies hand over required info to the Contractor (INFN)• INFN Team of experts (mechanical, RF, treatments, vacuum, etc.) check and

approve documents (“external” QC, process control)• “on-line” check of production quality (feedback to the Companies)

• Only if requirements are fulfilled, the cavity go on with production (Acceptance levels overcome)

• Non Conformities: If the required property of a component is not provided, a nonconformity report is emitted by the Company and further action are discussed and approved by the contractor: acceptance or quarantine

• Check list for any outcoming / incoming steps• INFN supervise the Quality Control by:

• Periodic Visit at the companies, scheduled meetings, actions of experts in case of problems.

Page 10: LASA Medium-β Cavity Progress Update Paolo Michelato 2 nd ESS Collaboration Meeting - SRF Elliptical Cavities 15 th December 2015.

QA / QC: How it will work (ESS)(Data Transfer, Flow of documents and data between INFN and Industry)

IndustryQC: responsibility of the Company;3 acceptance levels to overcome

Flow of documents for

the «external» QC

(LASA)

INFNCheck of all documents (parameters/process); experts do the check and acceptance;Prompt feedback to the Industry

Level Cavity status Needed documents If Level reached

One “Naked” cavity after fabrication

Mechanical Fabrication documents

Proceed to Level Two workflow

Two Cavity after surface treatments Treatment documents Proceed to Level

Three workflow

Three Cavity integration and last treatments

Integration and last treatment documents

Integrated cavity ready to be RF tested

Managing of documents/database

Industry must be released for each Al before going on with productionNCR must be emitted and repair action approved by INFN

Page 11: LASA Medium-β Cavity Progress Update Paolo Michelato 2 nd ESS Collaboration Meeting - SRF Elliptical Cavities 15 th December 2015.

Flow of cavities

INTERNAL Managing

SystemQuality Control

Industry

Cold RF test

Q0 vs. Eacc

CEASTRING

ASSEMBLY

CAVI

TY w

ith TA

NK

CAVITY with TANK MODULE ESS

Page 12: LASA Medium-β Cavity Progress Update Paolo Michelato 2 nd ESS Collaboration Meeting - SRF Elliptical Cavities 15 th December 2015.

QC / QA:How it will work (ESS)(Data Transfer, Flow of documents and data)

Cavity production data

INTERNAL Managing

SystemQuality Control

INFNIndustry

INFN Managing

system

Database(parameter

analysis)

INFN Experts Check

Cold RF test

Q0 vs. Eacc

CEASTRING

ASSEMBLY

CAVI

TY w

ith TA

NK

CAVITY with TANK

Documents for co

ld RF test acce

ptance

Documents for full equipped

cavity acceptance (for string assembly)

MODULE ESS

ESS(approval)

NCR

NCR

Page 13: LASA Medium-β Cavity Progress Update Paolo Michelato 2 nd ESS Collaboration Meeting - SRF Elliptical Cavities 15 th December 2015.

Clea

n Ro

om (I

SO7)

Clea

n Ro

om (I

SO4)

Example: ESS Prototype Cavities Treatment Flow