Accelerating Structure Feasibility W. Wuensch CLIC ACE 26-5-2009.

41
Accelerating Structure Feasibility W. Wuensch CLIC ACE 26-5-2009

Transcript of Accelerating Structure Feasibility W. Wuensch CLIC ACE 26-5-2009.

Page 1: Accelerating Structure Feasibility W. Wuensch CLIC ACE 26-5-2009.

Accelerating Structure Feasibility

W. WuenschCLIC ACE

26-5-2009

Page 2: Accelerating Structure Feasibility W. Wuensch CLIC ACE 26-5-2009.

Outline

• Requirement summary • Demonstration status• Near-term prospects• Contingency planning• Longer-term development

Page 3: Accelerating Structure Feasibility W. Wuensch CLIC ACE 26-5-2009.

Performance requirements oversimplified into a few numbers:

• Loaded gradient: 100 MV/m• Pulse length total/flat top: 240/160 ns• Breakdown rate in the range of a few 10-7/m• Minimum average a/λ: 0.11 (short range wake)• Maximum long range wake: 6 V/pC/m/mm

Page 4: Accelerating Structure Feasibility W. Wuensch CLIC ACE 26-5-2009.

Status

Page 5: Accelerating Structure Feasibility W. Wuensch CLIC ACE 26-5-2009.

Two T18_VG2.4_DISC Structures

Structure for KEK Test

Structure for SLAC Test

Page 6: Accelerating Structure Feasibility W. Wuensch CLIC ACE 26-5-2009.

95 100 105 110 11510

-7

10-6

10-5

10-4

Unloaded Gradient: MV/m

BK

D R

ate

: 1/p

uls

e/m

BKD Rate for 230ns

250hrs

500hrs

1200hrs

900hrs

500 1000 150095

100

105

110

115

Time with RF on: hrs

Gra

die

nt:

MV

/m

Gradient at 2e-6/pulse/m for 230ns pulse

Experiment DataPower Fit

For Constant Breakdown Rate

Unloaded Gradient at Different Conditioning Times

95 100 105 110 11510

-7

10-6

10-5

10-4

Unloaded Gradient: MV/m

BK

D P

oss

ibili

ty: 1

/pu

lse

/m

BKD Possibility for 230ns

250hrs

500hrs

1400hrs

1200hrs

900hrs

C. Adolphsen

Page 7: Accelerating Structure Feasibility W. Wuensch CLIC ACE 26-5-2009.

0 5 10 15 200

10

20

30

40

50

Cell No.

Pe

rce

nt o

f BK

D E

ven

ts

394 BKDs within 0~250hrs193 BKDs within 250~500hrs298 BKDs within 500~750hrs57 BKDs within 750~900hrs74 BKDs within 900~1000hrs34 BKDs within 1000~1200hrs24 BKDs within 1200~1400hrs

BKD Distribution Along Structure at Different Stages of Processing

Did not find visual evidence related to the hot cell in a post-run boroscope exam – typical of NLC/GLC structures, many of which had hot cells

C. Adolphsen

Page 8: Accelerating Structure Feasibility W. Wuensch CLIC ACE 26-5-2009.

BDR at 252nsec ACC breakdowns are defined as sudden breakdowns from normal running.

This excludes events following such breakdowns, typically only the very first pulse.

Even if include such associated breakdowns, the BDR stays within a factor two.

Comparable or larger number of FC-UP events are still to be investigated in their origin.

10-7

10-6

10-5

0.0001

80 85 90 95 100 105 110 115 120

BDR_252nsecBDR(ACC)

y = 3.0827e-19 * e (0.28174x) R= 0.99488

BDR(ACC)

Eacc

090501-090507

090313-090323

090401-090402090402-090403

090403-090407

090411-090414

Eacc are a little shifted artificilallyto show error bars clearly

090227-090305

T18 - KEK test

Page 9: Accelerating Structure Feasibility W. Wuensch CLIC ACE 26-5-2009.

Status summary

Two undamped T18 structures have run at an unloaded accelerating gradient at around 100 MV/m with the CLIC specified 4x10-7 /m breakdown rate with 230/250 ns rectangular pulses.

The CLIC flat-top is 160 ns, full width at 90% maximum gives effective pulse length, so we are above specification here.

Beam loading typically reduces the gradient by 15 to 20% (18% in CLIC_G), but this may be partially compensated by a corresponding decrease in breakdown rate, especially in strongly tapered structures. The magnitude of the beam loading effect is to be studied in two beam test stand.

The increased gradient was achieved through the use of high-power scaling laws in the design process.

Page 10: Accelerating Structure Feasibility W. Wuensch CLIC ACE 26-5-2009.

Near-term prospects

Page 11: Accelerating Structure Feasibility W. Wuensch CLIC ACE 26-5-2009.

Then next crucial step for the accelerating structure feasibility demonstration is to determine the influence of the damping features on gradient.

We believe that this effect will be small because,

- The (smaller) damping features of the NLC/JLC structures did not affect high-gradient performance. The H75 with manifold damping ran at 102 MV/m, 150 ns rectangular pulse, 6x10-6 BDR/structure for example.

- An artful analysis of the slotted-iris quadrant (HDS60 in particular) data indicates their (smaller) damping features did not affect performance. Requires geometric scaling of gradient, so not definitive demonstration.

HOWEVER the pulsed surface heating we have now, over 50 C, is significantly higher than other structures, around 20 C, and breakdown and pulsed surface heating could be linked in a number of ways.

We also move towards the nominal CLIC_G geometry which has what we now, through better understanding of iris scaling, believe is a more optimum iris range. This helps also with pulsed surface heating.

Page 12: Accelerating Structure Feasibility W. Wuensch CLIC ACE 26-5-2009.

undamped damped

0 2 4 6 8 10 12 14 16 180

50

100

150

200

250

300

iris number

P [

MW

] (b

lack

), E

s (

gre

en),

Ea (

red

) [M

V/m

],

T

[K

] (b

lue)

, S

c*50

[MW

/mm

2 ] (m

agen

ta)

14.822.9

158

249

3.1

5.1

81

134

60.8

42.9

Pinload = 60.8 MW, P

outload = 31.7 MW

Eff = 17.9 % tr = 18.2 ns, t

f = 33.3 ns, t

p = 269.3 ns

0 2 4 6 8 10 12 14 16 180

50

100

150

200

250

iris numberP

[M

W]

(bla

ck),

E s (

gre

en

), E a (

red

) [M

V/m

],

T

[K

] (b

lue),

S c*50 [

MW

/mm2 ]

(mag

en

ta)

53.7

86.6

165

242

3.7

5.0

84

129

65.6

39.1

Pinload = 65.6 MW, P

outload = 29.0 MW

Eff = 16.0 % tr = 22.2 ns, t

f = 38.7 ns, t

p = 278.6 ns

Transition from undamped to damped in the CLIC_vg1 type

Page 13: Accelerating Structure Feasibility W. Wuensch CLIC ACE 26-5-2009.

Structures under test

Page 14: Accelerating Structure Feasibility W. Wuensch CLIC ACE 26-5-2009.

Structures under test

Page 15: Accelerating Structure Feasibility W. Wuensch CLIC ACE 26-5-2009.

Structures are directly relevant for determining the effect of damping

Structure Built by Status Scheduled test date

Test location

TD18 #1 CERN Ready March, but on hold

SLAC

TD18 #2 KEK/SLAC Under assembly

September KEK

TD18 #3 KEK/SLAC Under assembly

August SLAC

TD24 #1 and 2 CERN Under assembly

August SLAC

TD18 QUAD #2 KEK Final assembly June KEK

If any one of these structures show a satisfactory gradient we will have demonstrated feasibility.

Page 16: Accelerating Structure Feasibility W. Wuensch CLIC ACE 26-5-2009.

Fabrication issues

Currently the majority of the test structures are made by KEK and SLAC due to their extensive experience in building low-breakdown rate structures. These structures are made by 1020 °C hydrogen brazing.

In recent months we have made our first brazed disk X-band structure since the early nineties. Our technique, 820 °C bond/braze, is basically the same as Fermilab’s.

Unfortunately this T18 ran very badly. We have cut it apart, compared it to measurements and analyzed it,

Page 17: Accelerating Structure Feasibility W. Wuensch CLIC ACE 26-5-2009.

T18_CERNBreakdown distribution of

T18Disk_SLAC (red, last 500hrs),

210~230 ns,110~120 MV/m

T18Disk_CERN (Blue,40hrs).

180 ns,45~49 MV/m

-100 0 100-5

0

5

10

15

20

25

30

35

40

Reflected Phase: Deg

Fill

ing

tim

e fo

r d

iffe

ren

t ce

ll: n

s

‘Hot’ phases

All iris - presence of small craters. S particles along grain boundaries – from bulk

Iris 12 – contamination (Ca, C)

Page 18: Accelerating Structure Feasibility W. Wuensch CLIC ACE 26-5-2009.

Reacting to the CERN T18 result

The poor performance was probably determined by a contamination on iris 12. However the discovery of presence of S particles from the bulk Cu is indicative of a more systematic problem – which calls into question our 30 GHz results…

Our response is to now assemble under a laminar flow hood to reduce the chances of contamination like that seen on iris 12. In addition we have also adopted the main difference with the Fermilab procedure, a 1000 °C disk pre-fire. One benefit is this seems to ensure that S stays disolved in the bulk and doesn’t collect on grain boundaries.

Our T18 was preceded at SLAC by a number of ‘exotic’ structures which also ran badly. These structures incorporated many new ideas – materials and quadrants - from the 30 GHz, 150 MV/m program. I believe these structures were not limited by fundamental issues and that we will return to the ideas one day and get them to work.

But the consequence is that CERN has a credibility problem for delivering good structures.

An excellent new team with a rigorous approach is learning to build structures and I believe we will resolve our problems soon (maybe already). We hope our collaborators are patient with us.

Making duplicate structures according to KEK/SLAC techniques (mainly high-temp bonding in H2 atmosphere) should help clear things up. And we must have a testing program here at CERN to get the timely feedback that we need.

Page 19: Accelerating Structure Feasibility W. Wuensch CLIC ACE 26-5-2009.

Contingency planning(also stuff which might be better

in the long run)

Page 20: Accelerating Structure Feasibility W. Wuensch CLIC ACE 26-5-2009.

Contingency planning – What can we do if the effect of the heavy damping features on gradient is significant?

A lot of course depends on why the gradient is reduced. But to cover this possibility we are actively considering different damping mechanisms.

In addition, the “classic” problem of surface damage through pulsed surface heating fatigue has not gone away. We have a ΔT of 56 °C in the nominal CLIC structure, which is very high for our baseline design of brazed copper disks.

We could end up with a 4000 hour test that goes fine, but the structures all fall apart after a couple of years.

We believe we have two types of solutions – damping configuration and material.

Page 21: Accelerating Structure Feasibility W. Wuensch CLIC ACE 26-5-2009.

Manifold damping – Roger Jones (now at Cockcroft Inst/ and Manchester U.) and Vasim Kahn are applying the DDS concept to 100 MV/m using our scaling laws. The high gradient performance of the damping has already demonstrated. However the much weaker damping means the bunch spacing must go up and efficiency down. That is unless we have the tolerances for dipole mode zero crossings… A CLIC DDS design and prototype is an FP7 activity.

Page 22: Accelerating Structure Feasibility W. Wuensch CLIC ACE 26-5-2009.

4th CLIC Advisory Committee (CLIC-ACE), 26th - 28th May 2009 22

Wake-field Suppression in CLIC_DDS Main Linac -Initial design

Circuit model provides rapid determination of optimal wakefield suppression results in a bandwidth of 3.6 (3.36 GHz) and f/ fc =20%.

Leftmost indicates the modal distribution and rightmost the coupled and uncoupled wakefield

Four-fold interleaving of successive structures results in excellent wake-field suppression at the location of each bunch

Meets CLIC beam dynamics requirements!

However, breakdown considerations require a redesign with additional constraints imposed

Envelope of Wakefield for Single 25-Cell Structure (Q ~ ∞)

Wakefield for 8-Fold Interleaved Structure (Q ~ ∞)

Kick Factor Weighted Density Function

Envelope of Wakefield for 4-Fold Interleaved Structure (Finite Q )

dn/df

Kdn/dfCoupled

Uncoupled

Page 23: Accelerating Structure Feasibility W. Wuensch CLIC ACE 26-5-2009.

Choke mode damping

Valery’s first try at a choke mode cavity didn’t work very well at high power. However Alexej has proposed a new configuration which will be high-power tested with a CD10-choke structure. Igor’s choke flange is working beautifully.

We will study a choke mode CLIC structure in a collaboration with Tsinghua University and they will build a prototype. Fellow hopefully approved by end of week.

Pulse surface heating is way down compared to waveguide damping but so is the damping strength. Plus this assembly can be done without brazing, so high-strength copper alloys for example can be used.

Probably implies a larger bunch spacing. Damping loads are going to be tough…

Page 24: Accelerating Structure Feasibility W. Wuensch CLIC ACE 26-5-2009.

Slotted-iris structures made from quadrants

Excellent damping characteristics, especially with iris slots. Full range of materials and preparation techniques possible.We had hints of success but mostly problems. The HDS60 had a performance consistent with brazed disks if you use scaling laws. The HDX-11 worked well for about 20 hours and an HDS4 worked well for about 7 hours. Is the subsequent deterioration fundamental or due to specific rf design features? Other quadrants didn’t work well but were these problems fundamental or technical?

160 mm

30 GHz HDS60 X-band HDX11

Page 25: Accelerating Structure Feasibility W. Wuensch CLIC ACE 26-5-2009.

Longer-term prospects

Page 26: Accelerating Structure Feasibility W. Wuensch CLIC ACE 26-5-2009.

Quantitative approach to high-gradients and efficient linacs

Comprehensive rf design

High-power scaling laws

Simulation and theory

Diagnostics

Rf experimentsDc spark

experiments

Integrated rf and beam dynamics

optimization

Page 27: Accelerating Structure Feasibility W. Wuensch CLIC ACE 26-5-2009.

The importance of iris aperture

It is quite clear that iris aperture is the single most important structure parameter for both beam dynamics and gradient and consequently for overall efficiency.

The computation of short range wakes is well established. Original theory is by Karl Bane and others. We have even had a EuroTeV fellow (Riccardo Zennaro) to cross check theory with computation by GDFDL in our parameter range.

Analysis of existing high gradient data combined with some physical reasoning by Alexej and myself has resulted in gradient scaling parameters, P/C and Sc, which reflect and give, respectively, a very strong dependence of gradient on iris diameter.

To determine this crucial dependency more precisely, and to give input for further gradient scaling studies, a series of 10 cell structure tests, called C10’s, with different iris sizes has been launched. Fabrication is at KEK and SLAC.

Page 28: Accelerating Structure Feasibility W. Wuensch CLIC ACE 26-5-2009.

Schematic View for C10 Structures - II

Subassembly for Test Cells

Page 29: Accelerating Structure Feasibility W. Wuensch CLIC ACE 26-5-2009.

C10 structures

Page 30: Accelerating Structure Feasibility W. Wuensch CLIC ACE 26-5-2009.

Other important effects

The next step will be to quantify the effect of tapering, which luckily seems to have a beneficial effect. Comparison of the T18, very strongly tapered, and the T24 will address this issue.

We believe this is due to transient power flow into a breakdown. And have made a 30 GHz test to address this issue, the “speed-bump”

Gradient might also be dependant on group velocity. To investigate this we have made the 30 GHz TM020 structure.

Page 31: Accelerating Structure Feasibility W. Wuensch CLIC ACE 26-5-2009.

31

Speed bump (TM03)

R=14.398 mm

R_iris= 2.428 mm

Iris_thickness= 1mm0

0.01

0.02

0.03

0.04

0.05

0.06

0 1 2 3 4 5

cell #

vg

/c

2nd mode speed bump

regular cell nominal value

3rd mode speed bump

3rd mode,final version

Goal : « protect » the structure by lowering Vg in the first cell (usually the most damaged).

Tested in both direction :

• RF fed from the input (4.1×106 pulses, 2186 breakdown) → the speed bump plays its role• RF from the output (1.7×106 pulses, 501 breakdown) → the speed bump has no effect

Test structure in disks: 30 cell and identical mode launcher of the “conventional” 2π/3 Ø 3.5 mm

Page 32: Accelerating Structure Feasibility W. Wuensch CLIC ACE 26-5-2009.

65 70 75 80 85 90 95 100

10-6

10-5

10-4

10-3

10-2

Peak gradient (MV/m)

Bre

akd

ow

n r

ate

C30-sbUpper limits

-- Conventionnal 3.5mm structure

Speed bump (TM03) - results

No effect observed on the breakdown rate : similar results in both directions and for the 3.5 mm structure (same design without speed bump), but…

Standard disc 1 Standard disc 28

Page 33: Accelerating Structure Feasibility W. Wuensch CLIC ACE 26-5-2009.

33

• Same phase advance• Same P/c• Same aperture and iris shape• Same field configuration in the iris region

Is it possible to change some global parameter without changing local field distribution?

TM01 regular cell

“reference”

TM02 regular cell

Only by changing the propagating mode.

• Different group velocity: 4.7% and 2%• Different R/Q: 29 kΩ/m and 12 kΩ/m but

50 55 60 65 70 75 80 85 90 95 100

10-4

10-3

10-2

Peak gradient (MV/m)

Bre

akdo

wn

rate

TM02 (very) preliminary results3.5 mmC30-SBReversed C30-SB

1

2

3

4

5

6

7

8

9

10

11

12

13

14

PREL

IMIN

ARY

TM02 structure – separate effect of group velocity and local fields

Page 34: Accelerating Structure Feasibility W. Wuensch CLIC ACE 26-5-2009.

0

2E+12

4E+12

6E+12

8E+12

1E+13

1.2E+13

1.4E+13

1.6E+13

0 5 10 15 20E (MeV)

Da

rk C

urr

en

t (a

.u.)

DC SUM Cell 1-20DC SUM Cell 1-16

Dark current: Direct comparison between simulation and measurement in the T18 structure.

Simulation by SLAC ACG using Track3P. Fermilab is starting tracking simulation activities too.

GVGVPM PMAM

Sl i t

FC

E

E

I P

Louni nel oad

Otsukal oad

DC

I PH

VAC

I nsulVAC

I PDC H

H

Vari an I P

187

KX03 425

FC

I P

Load

Vari anI P

Q-mass

WC WCFC

FC

VAC DC

230

Measured at KEK

Page 35: Accelerating Structure Feasibility W. Wuensch CLIC ACE 26-5-2009.

Multiscale Modelling of Vacuum Arcs in Breakdowns

Flyura Djurabekova, Helga Timkó, Kai Nordlund

Helsinki Institute of Physics and CERN

Page 36: Accelerating Structure Feasibility W. Wuensch CLIC ACE 26-5-2009.

36 May 2009 H. Timkó, CERN & HIP

Multiscale model

Our model corresponds to the above 3 phases.

Stage 1: Charge distribution at the surfaceMethod: DFT with external electric field

Stage 2: Atomic motion & evaporation Method: Hybrid ED&MD modelClassical MD

Solution of Laplace equation

Stage 3: Evolution of surface morphology due to the given charge distribution Method: Kinetic Monte Carlo

Stage 4: Plasma evolution, burning of arcMethod: Particle-in-Cell (PIC)

Feedback: Electron & ion & cluster emission ions

Feedback: Energy & flux of bombarding ions Stage 5: Surface damage due to the

intense ion bombardment from plasmaMetod: Arc MD

Onset of plasma

Page 37: Accelerating Structure Feasibility W. Wuensch CLIC ACE 26-5-2009.

37 May 2009 H. Timkó, CERN & HIP

Achievements1. Onset: direct field evaporation from surfaces and tips

could be simulated

2. Plasma build-up: currently under development is a 1D

PIC code (from MPG) that used a simplified model; now

we are modelling the experimental DC setup including

All possible collisions, experimental and simulated

sputtering yields, secondary electron yield

Dynamic field emission and erosion of the tip

3. Cratering: using PIC input (flux & energy distribution of

incident ions), erosion and sputtering was simulated

Comparing arc plasma bombardment and thermal

heating, we found that:- threshold, corresp. to the melting point- Only in the case of plasma bombardment we see a heat

spike & cluster emission above the threshold and experimentally seen complex crater shapes can form

threshold

Page 38: Accelerating Structure Feasibility W. Wuensch CLIC ACE 26-5-2009.

Comparison between effect of thermal heating and ion bombardment on surface – same amount of energy but

different mechanism

Page 39: Accelerating Structure Feasibility W. Wuensch CLIC ACE 26-5-2009.

Breakdown diagnostics Jan W. Kovermann

The connection between simulation and experiment

Emitted currents-Dark current spectrum-OTR -X-rays-Trigger mechanism-Missing energy-Breakdown rate-Ion currents-Fowler-Nordheim distribution

Plasma characteristics-Time structure-Physical dimension (imaging)-Ion species (opt. spectroscopy)-Ion currents-Vacuum behaviour

Surfaces-Crater morphology-Material diagnostics-Fatigue process

Page 40: Accelerating Structure Feasibility W. Wuensch CLIC ACE 26-5-2009.

Breakdown diagnostics Jan W. Kovermann

Breakdown diagnostics: some results

RF DC

OTR

(Cop

per)

Opt

. spe

ctro

scop

y

Found Cu I, Cu II, Cu III ionsWill be measured soon at

Page 41: Accelerating Structure Feasibility W. Wuensch CLIC ACE 26-5-2009.

Breakdown diagnostics Jan W. Kovermann

Breakdown diagnostics: further measurements

RF DC

RF (I

,Q),

Xray

, FC

@30

GH

z

Curr

ent,

volta

ge a

nd d

elay

?SE

M o

f sin

gle

brea

kdow

ns